Vivid Tower construction progress
The registered completion date for Vivid Tower in Al Barsha South Fifth is November 2026. At the last site inspection, in August 2026, it was 12% built. The developer is Obj1 Real Estate Development.
12%
Built, at the site inspection of 12 August 2026
Running behind its date
- Registered completion date
- November 2026
- Finish at recent pace
- May 2033
- Construction started
- January 2025
- First registered
- March 2025
- Developer
- Obj1 Real Estate Development
- Community
- Al Barsha South Fifth
- Units
- 147
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- فيفيد تاور
- Project number
- 3380
- Site inspections
- 4
Schedule
Between December 2025 and August 2026 the site added about 1.1 points a month. At that rate it would finish around May 2033, more than three months after its registered date of November 2026.
Site inspections
12 August 2026
12%+4.8 pts
29 April 2026
7.5%+3.3 pts
29 December 2025
4.3%+4.3 pts
11 December 2024
0%
Context
Al Barsha South Fifth has 2 projects under construction, 42% built on average.
Obj1 Real Estate Development has 14 projects under construction in Dubai; 3 have passed their registered completion date.
Own a unit in Vivid Tower?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Vivid Tower handover date?
- The registered completion date is November 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2033. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Vivid Tower?
- Vivid Tower was 12% built at the site inspection on 12 August 2026. The site has been inspected 4 times since December 2024. The Land Department took 20 site photos at its inspections.
- Is Vivid Tower delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2026.
- Who is building Vivid Tower?
- The registered developer is Obj1 Real Estate Development. It has 13 other projects under construction in Dubai.
- Which bank holds the escrow account for Vivid Tower?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Luminar Tower 1Also by Obj1 Real Estate Development. 40%, Due October 2026, passed.
- Evergrin HouseAlso by Obj1 Real Estate Development. 55%, Due June 2026, passed.
- Luminar Tower 2Also by Obj1 Real Estate Development. 40%, Due October 2026, passed.
- Luminar Tower 3Also by Obj1 Real Estate Development. 18%, Due March 2027.
- Miami By SdNearby in Al Barsha South Fifth. 71%, Due July 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.