Vivid Tower construction progress

Vivid Tower in Al Barsha South Fifth is 12% built at the Land Department inspection of August 2026. Developer Obj1 Real Estate Development. Completion registered for November 2026.

12%

Built, at the Land Department site inspection of 12 August 2026

Running behind its date

Completion date (Land Department)
November 2026
Finish at recent pace
May 2033
Construction started
January 2025
Registered with the Land Department
March 2025
Community
Al Barsha South Fifth
Units
147
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
فيفيد تاور
Land Department project number
3380
Land Department site inspections
4

Schedule

Between December 2025 and August 2026 the site added about 1.1 points a month. At that rate it would finish around May 2033, more than three months after the November 2026 date registered with the Land Department.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

12 August 2026

12%+4.8 pts

  • Vivid Tower construction site, Land Department inspection photo 1, 12 August 2026
  • Vivid Tower construction site, Land Department inspection photo 2, 12 August 2026
  • Vivid Tower construction site, Land Department inspection photo 3, 12 August 2026
  • Vivid Tower construction site, Land Department inspection photo 4, 12 August 2026

29 April 2026

7.5%+3.3 pts

  • Vivid Tower construction site, Land Department inspection photo 1, 29 April 2026
  • Vivid Tower construction site, Land Department inspection photo 2, 29 April 2026
  • Vivid Tower construction site, Land Department inspection photo 3, 29 April 2026
  • Vivid Tower construction site, Land Department inspection photo 4, 29 April 2026

29 December 2025

4.3%+4.3 pts

  • Vivid Tower construction site, Land Department inspection photo 1, 29 December 2025
  • Vivid Tower construction site, Land Department inspection photo 2, 29 December 2025
  • Vivid Tower construction site, Land Department inspection photo 3, 29 December 2025
  • Vivid Tower construction site, Land Department inspection photo 4, 29 December 2025

11 December 2024

0%

  • Vivid Tower construction site, Land Department inspection photo 1, 11 December 2024
  • Vivid Tower construction site, Land Department inspection photo 2, 11 December 2024

All 20 site photos, by inspection date

Context

Al Barsha South Fifth has 2 projects under construction, 42% built on average.

Obj1 Real Estate Development has 14 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Vivid Tower?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Vivid Tower be completed?
The completion date registered with the Dubai Land Department is November 2026. At the pace of its recent inspections the site would reach 100% around May 2033. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Vivid Tower is built?
12%, measured at the Land Department site inspection on 12 August 2026. The Land Department engineers have inspected the site 4 times since December 2024.
Is Vivid Tower delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2026.
Who is building Vivid Tower?
The registered developer is Obj1 Real Estate Development. It has 13 other projects under construction in Dubai.
Which bank holds the escrow account for Vivid Tower?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.