Lridian Park 1 construction progress
Lridian Park 1 in Jumeirah Village Circle is 33% built at the Land Department inspection of August 2026. Developer Obj1 Real Estate Development. Completion registered for February 2027.
33%
Built, at the Land Department site inspection of 17 August 2026
Running behind its date
- Completion date (Land Department)
- February 2027
- Finish at recent pace
- February 2028
- Construction started
- August 2025
- Registered with the Land Department
- October 2025
- Developer
- Obj1 Real Estate Development
- Community
- Jumeirah Village Circle
- Units
- 76
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- 1 اريديان بارك
- Land Department project number
- 3764
- Land Department site inspections
- 4
Schedule
Between February 2026 and August 2026 the site added about 3.8 points a month. At that rate it would finish around February 2028, more than three months after the February 2027 date registered with the Land Department.
Site inspections
17 August 2026
33%+17 pts
19 May 2026
16%+6.2 pts
12 February 2026
9.7%+9.7 pts
22 May 2025
0%
Context
Jumeirah Village Circle has 119 projects under construction, 40% built on average.
Obj1 Real Estate Development has 14 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Lridian Park 1?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Lridian Park 1 be completed?
- The completion date registered with the Dubai Land Department is February 2027. At the pace of its recent inspections the site would reach 100% around February 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Lridian Park 1 is built?
- 33%, measured at the Land Department site inspection on 17 August 2026. The Land Department engineers have inspected the site 4 times since May 2025.
- Is Lridian Park 1 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2027.
- Who is building Lridian Park 1?
- The registered developer is Obj1 Real Estate Development. It has 13 other projects under construction in Dubai.
- Which bank holds the escrow account for Lridian Park 1?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Luminar Tower 1Also by Obj1 Real Estate Development. 33%.
- Evergrin HouseAlso by Obj1 Real Estate Development. 55%, Due June 2026, passed.
- Luminar Tower 2Also by Obj1 Real Estate Development. 31%, Due October 2026.
- Vivid TowerAlso by Obj1 Real Estate Development. 12%, Due November 2026.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 42%, Due January 2013, passed.
- Serenity Lakes 2Nearby in Jumeirah Village Circle. 50%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 90%, Due April 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)