Verdania 4 construction progress
The registered completion date for Verdania 4 is June 2028. At the last site inspection, in October 2026, it was 0.7% built. The developer is Obj1 Real Estate Development.
0.7%
Built, at the site inspection of 28 October 2026
Running behind its date
- Registered completion date
- June 2028
- Finish at recent pace
- December 2157
- Construction started
- December 2025
- First registered
- August 2026
- Developer
- Obj1 Real Estate Development
- Units
- 394
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- فيردانيا 4
- Project number
- 4271
- Site inspections
- 2
Schedule
Between December 2025 and October 2026 the site added about 0.1 points a month. At that rate it would finish around December 2157, more than three months after its registered date of June 2028.
Site inspections
28 October 2026
0.7%+0.7 pts
4 December 2025
0%
Context
Obj1 Real Estate Development has 14 projects under construction in Dubai; 3 have passed their registered completion date.
Own a unit in Verdania 4?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Verdania 4 handover date?
- The registered completion date is June 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2157. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Verdania 4?
- Verdania 4 was 0.7% built at the site inspection on 28 October 2026. The site has been inspected 2 times since December 2025. The Land Department took 8 site photos at its inspections.
- Is Verdania 4 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
- Who is building Verdania 4?
- The registered developer is Obj1 Real Estate Development. It has 13 other projects under construction in Dubai.
- Which bank holds the escrow account for Verdania 4?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Luminar Tower 1Also by Obj1 Real Estate Development. 40%, Due October 2026, passed.
- Evergrin HouseAlso by Obj1 Real Estate Development. 55%, Due June 2026, passed.
- Luminar Tower 2Also by Obj1 Real Estate Development. 40%, Due October 2026, passed.
- Vivid TowerAlso by Obj1 Real Estate Development. 12%, Due November 2026.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.