Skip to content

Verdania 1 construction progress

The registered completion date for Verdania 1 in Dubai Land Residence Complex is March 2027. At the last site inspection, in October 2026, it was 31% built. The developer is Obj1 Real Estate Development.

31%

Built, at the site inspection of 28 October 2026

Running behind its date

Registered completion date
March 2027
Finish at recent pace
April 2029
Construction started
March 2025
First registered
June 2025
Units
208
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
فيردانيا 1
Project number
3543
Site inspections
5

Schedule

Between February 2026 and October 2026 the site added about 2.3 points a month. At that rate it would finish around April 2029, more than three months after its registered date of March 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

28 October 2026

31%+14 pts

  • Verdania 1 construction site, inspection photo 1, 28 October 2026
  • Verdania 1 construction site, inspection photo 2, 28 October 2026
  • Verdania 1 construction site, inspection photo 3, 28 October 2026
  • Verdania 1 construction site, inspection photo 4, 28 October 2026

18 June 2026

17%+4.4 pts

  • Verdania 1 construction site, inspection photo 1, 18 June 2026
  • Verdania 1 construction site, inspection photo 2, 18 June 2026
  • Verdania 1 construction site, inspection photo 3, 18 June 2026
  • Verdania 1 construction site, inspection photo 4, 18 June 2026

24 February 2026

12%+9.3 pts

  • Verdania 1 construction site, inspection photo 1, 24 February 2026
  • Verdania 1 construction site, inspection photo 2, 24 February 2026
  • Verdania 1 construction site, inspection photo 3, 24 February 2026
  • Verdania 1 construction site, inspection photo 4, 24 February 2026

28 July 2025

3.0%+3.0 pts

  • Verdania 1 construction site, inspection photo 1, 28 July 2025
  • Verdania 1 construction site, inspection photo 2, 28 July 2025
  • Verdania 1 construction site, inspection photo 3, 28 July 2025
  • Verdania 1 construction site, inspection photo 4, 28 July 2025

26 May 2025

0%

  • Verdania 1 construction site, inspection photo 1, 26 May 2025
  • Verdania 1 construction site, inspection photo 2, 26 May 2025

All 23 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Obj1 Real Estate Development has 14 projects under construction in Dubai; 3 have passed their registered completion date.

Own a unit in Verdania 1?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Verdania 1 handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Verdania 1?
Verdania 1 was 31% built at the site inspection on 28 October 2026. The site has been inspected 5 times since May 2025. The Land Department took 23 site photos at its inspections.
Is Verdania 1 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Verdania 1?
The registered developer is Obj1 Real Estate Development. It has 13 other projects under construction in Dubai.
Which bank holds the escrow account for Verdania 1?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.