Luminar Tower 3 construction progress
The registered completion date for Luminar Tower 3 in Jumeirah Village Triangle is March 2027. At the last site inspection, in October 2026, it was 18% built. The developer is Obj1 Real Estate Development.
18%
Built, at the site inspection of 28 October 2026
Running behind its date
- Registered completion date
- March 2027
- Finish at recent pace
- January 2033
- Construction started
- January 2025
- First registered
- December 2024
- Developer
- Obj1 Real Estate Development
- Community
- Jumeirah Village Triangle
- Units
- 188
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- لومينار تاور ثري
- Project number
- 3443
- Site inspections
- 6
Schedule
Between December 2025 and October 2026 the site added about 1.1 points a month. At that rate it would finish around January 2033, more than three months after its registered date of March 2027.
Site inspections
28 October 2026
18%+4.8 pts
17 July 2026
14%+5.1 pts
30 April 2026
8.5%+1.3 pts
23 December 2025
7.2%+5.1 pts
3 June 2025
2.0%+2.0 pts
4 December 2024
0%
Context
Jumeirah Village Triangle has 29 projects under construction, 27% built on average.
Obj1 Real Estate Development has 14 projects under construction in Dubai; 3 have passed their registered completion date.
Own a unit in Luminar Tower 3?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Luminar Tower 3 handover date?
- The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2033. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Luminar Tower 3?
- Luminar Tower 3 was 18% built at the site inspection on 28 October 2026. The site has been inspected 6 times since December 2024. The Land Department took 23 site photos at its inspections.
- Is Luminar Tower 3 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
- Who is building Luminar Tower 3?
- The registered developer is Obj1 Real Estate Development. It has 13 other projects under construction in Dubai.
- Which bank holds the escrow account for Luminar Tower 3?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Luminar Tower 1Also by Obj1 Real Estate Development. 40%, Due October 2026, passed.
- Evergrin HouseAlso by Obj1 Real Estate Development. 55%, Due June 2026, passed.
- Luminar Tower 2Also by Obj1 Real Estate Development. 40%, Due October 2026, passed.
- Vivid TowerAlso by Obj1 Real Estate Development. 12%, Due November 2026.
- Paradise OneNearby in Jumeirah Village Triangle. 70%, Due April 2027.
- Silver StallionsNearby in Jumeirah Village Triangle. 12%, Due December 2017, passed.
- Fashionz 1 By DanubeNearby in Jumeirah Village Triangle. 40%.
- Volga TowerNearby in Jumeirah Village Triangle. 51%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.





.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)