Luminar Tower 3 construction progress

The registered completion date for Luminar Tower 3 in Jumeirah Village Triangle is March 2027. At the last site inspection, in October 2026, it was 18% built. The developer is Obj1 Real Estate Development.

18%

Built, at the site inspection of 28 October 2026

Running behind its date

Registered completion date
March 2027
Finish at recent pace
January 2033
Construction started
January 2025
First registered
December 2024
Units
188
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
لومينار تاور ثري
Project number
3443
Site inspections
6

Schedule

Between December 2025 and October 2026 the site added about 1.1 points a month. At that rate it would finish around January 2033, more than three months after its registered date of March 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

28 October 2026

18%+4.8 pts

  • Luminar Tower 3 construction site, inspection photo 1, 28 October 2026
  • Luminar Tower 3 construction site, inspection photo 2, 28 October 2026
  • Luminar Tower 3 construction site, inspection photo 3, 28 October 2026
  • Luminar Tower 3 construction site, inspection photo 4, 28 October 2026

17 July 2026

14%+5.1 pts

  • Luminar Tower 3 construction site, inspection photo 1, 17 July 2026
  • Luminar Tower 3 construction site, inspection photo 2, 17 July 2026
  • Luminar Tower 3 construction site, inspection photo 3, 17 July 2026
  • Luminar Tower 3 construction site, inspection photo 4, 17 July 2026

30 April 2026

8.5%+1.3 pts

  • Luminar Tower 3 construction site, inspection photo 1, 30 April 2026
  • Luminar Tower 3 construction site, inspection photo 2, 30 April 2026
  • Luminar Tower 3 construction site, inspection photo 3, 30 April 2026
  • Luminar Tower 3 construction site, inspection photo 4, 30 April 2026

23 December 2025

7.2%+5.1 pts

  • Luminar Tower 3 construction site, inspection photo 1, 23 December 2025
  • Luminar Tower 3 construction site, inspection photo 2, 23 December 2025
  • Luminar Tower 3 construction site, inspection photo 3, 23 December 2025
  • Luminar Tower 3 construction site, inspection photo 4, 23 December 2025

3 June 2025

2.0%+2.0 pts

  • Luminar Tower 3 construction site, inspection photo 1, 3 June 2025
  • Luminar Tower 3 construction site, inspection photo 2, 3 June 2025
  • Luminar Tower 3 construction site, inspection photo 3, 3 June 2025
  • Luminar Tower 3 construction site, inspection photo 4, 3 June 2025

4 December 2024

0%

  • Luminar Tower 3 construction site, inspection photo 1, 4 December 2024
  • Luminar Tower 3 construction site, inspection photo 2, 4 December 2024

All 23 site photos, by inspection date

Context

Jumeirah Village Triangle has 29 projects under construction, 27% built on average.

Obj1 Real Estate Development has 14 projects under construction in Dubai; 3 have passed their registered completion date.

Own a unit in Luminar Tower 3?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Luminar Tower 3 handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2033. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Luminar Tower 3?
Luminar Tower 3 was 18% built at the site inspection on 28 October 2026. The site has been inspected 6 times since December 2024. The Land Department took 23 site photos at its inspections.
Is Luminar Tower 3 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Luminar Tower 3?
The registered developer is Obj1 Real Estate Development. It has 13 other projects under construction in Dubai.
Which bank holds the escrow account for Luminar Tower 3?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.