Elm At Park Five construction progress

Elm At Park Five in International Media Production Zone is 16% built at the Land Department inspection of September 2026. Developer Deyaar Development. Completion registered for June 2027.

16%

Built, at the Land Department site inspection of 3 September 2026

Running behind its date

Completion date (Land Department)
June 2027
Finish at recent pace
June 2030
Construction started
April 2025
Registered with the Land Department
December 2024
Units
532
Escrow bank
Dubai Islamic Bank
Name in Arabic
إيلم في بارك فايف
Land Department project number
3343
Land Department site inspections
3

Schedule

Between June 2026 and September 2026 the site added about 1.9 points a month. At that rate it would finish around June 2030, more than three months after the June 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

3 September 2026

16%+5.2 pts

  • Elm At Park Five construction site, Land Department inspection photo 1, 3 September 2026
  • Elm At Park Five construction site, Land Department inspection photo 2, 3 September 2026
  • Elm At Park Five construction site, Land Department inspection photo 3, 3 September 2026
  • Elm At Park Five construction site, Land Department inspection photo 4, 3 September 2026

10 June 2026

11%+11 pts

  • Elm At Park Five construction site, Land Department inspection photo 1, 10 June 2026
  • Elm At Park Five construction site, Land Department inspection photo 2, 10 June 2026
  • Elm At Park Five construction site, Land Department inspection photo 3, 10 June 2026
  • Elm At Park Five construction site, Land Department inspection photo 4, 10 June 2026

5 November 2024

0%

  • Elm At Park Five construction site, Land Department inspection photo 1, 5 November 2024
  • Elm At Park Five construction site, Land Department inspection photo 2, 5 November 2024

All 12 site photos, by inspection date

Context

International Media Production Zone has 15 projects under construction, 22% built on average.

Deyaar Development has 10 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Elm At Park Five?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Elm At Park Five be completed?
The completion date registered with the Dubai Land Department is June 2027. At the pace of its recent inspections the site would reach 100% around June 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Elm At Park Five is built?
16%, measured at the Land Department site inspection on 3 September 2026. The Land Department engineers have inspected the site 3 times since November 2024.
Is Elm At Park Five delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
Who is building Elm At Park Five?
The registered developer is Deyaar Development. It has 9 other projects under construction in Dubai.
Which bank holds the escrow account for Elm At Park Five?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.