Deyaar Development projects under construction
Deyaar Development has 9 projects under construction in Dubai. On average they are 27% built. 1 has passed its registered completion date. The next one due is Ember At Park Five, in June 2027.
- Rosalia ResidencesAl Furjan93%No date set
- Mar CasaDubai Maritime City67%Due October 2026, passed
- Eleve By DeyaarDown Town Jabal Ali20%No date set
- Ember At Park FiveInternational Media Production Zone18%Due June 2027
- Elm At Park FiveInternational Media Production Zone16%Due June 2027
- Neem At Park FiveInternational Media Production Zone15%Due December 2027
- Ivy At Park FiveInternational Media Production Zone6.3%Due December 2027
- Alder At Park FiveInternational Media Production Zone6.1%Due December 2027
- Downtown ResidencesBusiness Bay1.3%Due December 2030
Questions
How many projects is Deyaar Development building in Dubai?
9 projects are under construction, 27% built on average at the latest site inspections.
Which Deyaar Development projects finish next?
By registered completion date: Ember At Park Five (June 2027, 18% built), Elm At Park Five (June 2027, 16% built) and Neem At Park Five (December 2027, 15% built). RERA asks developers to update these dates as projects move, so check the register before relying on one.
Are any Deyaar Development projects delayed?
1 of its 9 projects have passed the registered completion date, among them Mar Casa. A project counts as late once its registered completion date has passed before it reaches 100%.
Where is Deyaar Development building?
Its projects are in International Media Production Zone (5), Al Furjan (1) and Business Bay (1), and 2 other communities.
Reading these figures
Each percentage is the share of construction recorded at the latest site inspection. The completion date is the one the developer registered, and RERA asks developers to update it when it reviews a project. Open a project to see its latest inspections, the site photos and whether it is keeping pace with that date.
What happens at handover and how to snag a new home cover the steps after 100%.
Source: the Dubai Land Department’s Mashrooi register, read daily. Projects listed as cancelled or finished are not shown.