Mar Casa construction progress

Mar Casa in Dubai Maritime City was registered to complete in October 2026 and is still under construction. At the last site inspection, in October 2026, it was 67% built. The developer is Deyaar Development.

67%

Built, at the site inspection of 29 October 2026

1 months past its registered completion date

Registered completion date
October 2026
Finish at recent pace
September 2027
Construction started
September 2023
First registered
March 2023
Units
585
Escrow bank
First Abu Dhabi Bank
Name in Arabic
ماركاسا
Project number
2589
Site inspections
8

Schedule

Mar Casa was registered to complete in October 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 3.2 points a month. Kept at that rate, the site would reach 100% around September 2027.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

29 October 2026

67%+10 pts

  • Mar Casa construction site, inspection photo 1, 29 October 2026
  • Mar Casa construction site, inspection photo 2, 29 October 2026
  • Mar Casa construction site, inspection photo 3, 29 October 2026
  • Mar Casa construction site, inspection photo 4, 29 October 2026

4 August 2026

56%+8.2 pts

  • Mar Casa construction site, inspection photo 1, 4 August 2026
  • Mar Casa construction site, inspection photo 2, 4 August 2026
  • Mar Casa construction site, inspection photo 3, 4 August 2026
  • Mar Casa construction site, inspection photo 4, 4 August 2026

4 May 2026

48%+14 pts

  • Mar Casa construction site, inspection photo 1, 4 May 2026
  • Mar Casa construction site, inspection photo 2, 4 May 2026
  • Mar Casa construction site, inspection photo 3, 4 May 2026
  • Mar Casa construction site, inspection photo 4, 4 May 2026

22 December 2025

34%+14 pts

  • Mar Casa construction site, inspection photo 1, 22 December 2025
  • Mar Casa construction site, inspection photo 2, 22 December 2025
  • Mar Casa construction site, inspection photo 3, 22 December 2025
  • Mar Casa construction site, inspection photo 4, 22 December 2025

11 June 2025

20%+5.4 pts

  • Mar Casa construction site, inspection photo 1, 11 June 2025
  • Mar Casa construction site, inspection photo 2, 11 June 2025
  • Mar Casa construction site, inspection photo 3, 11 June 2025
  • Mar Casa construction site, inspection photo 4, 11 June 2025

2 January 2025

15%+10 pts

  • Mar Casa construction site, inspection photo 1, 2 January 2025
  • Mar Casa construction site, inspection photo 2, 2 January 2025
  • Mar Casa construction site, inspection photo 3, 2 January 2025
  • Mar Casa construction site, inspection photo 4, 2 January 2025

8 March 2024

4.9%+4.9 pts

  • Mar Casa construction site, inspection photo 1, 8 March 2024
  • Mar Casa construction site, inspection photo 2, 8 March 2024
  • Mar Casa construction site, inspection photo 3, 8 March 2024
  • Mar Casa construction site, inspection photo 4, 8 March 2024

1 March 2023

0%

  • Mar Casa construction site, inspection photo 1, 1 March 2023
  • Mar Casa construction site, inspection photo 2, 1 March 2023

All 53 site photos, by inspection date

Context

Dubai Maritime City has 23 projects under construction, 32% built on average.

Deyaar Development has 9 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Mar Casa?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Mar Casa handover date?
The registered completion date was October 2026, and the register still lists Mar Casa as under construction. At the pace of its recent inspections the site would reach 100% around September 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Mar Casa?
Mar Casa was 67% built at the site inspection on 29 October 2026. The site has been inspected 8 times since March 2023. The Land Department took 53 site photos at its inspections.
Is Mar Casa delayed?
Yes. Its registered completion date of October 2026 has passed and the project is still listed as under construction.
Who is building Mar Casa?
The registered developer is Deyaar Development. It has 8 other projects under construction in Dubai.
Which bank holds the escrow account for Mar Casa?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.