Eleve By Deyaar construction progress
No completion date is registered for Eleve By Deyaar in Down Town Jabal Ali yet. At the last site inspection, in September 2026, it was 20% built. The developer is Deyaar Development.
20%
Built, at the site inspection of 24 September 2026
- Finish at recent pace
- October 2032
- Construction started
- October 2024
- First registered
- February 2024
- Developer
- Deyaar Development
- Community
- Down Town Jabal Ali
- Units
- 818
- Escrow bank
- Emirates NBD
- Name in Arabic
- إليفي من ديار
- Project number
- 2965
- Site inspections
- 6
Schedule
Since November 2025 Eleve By Deyaar has added about 1.1 points a month. At that rate the site reaches 100% around October 2032. No completion date is on record to compare it with.
Site inspections
24 September 2026
20%+4.3 pts
23 June 2026
16%+2.8 pts
19 March 2026
13%+3.7 pts
28 November 2025
9.2%
27 November 2025
9.2%+9.2 pts
16 February 2024
0%
Context
Down Town Jabal Ali has 4 projects under construction, 6.5% built on average.
Deyaar Development has 9 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Eleve By Deyaar?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Eleve By Deyaar handover date?
- No completion date is on record for Eleve By Deyaar yet. Handover follows completion, so there is no date to give.
- What is the latest construction update on Eleve By Deyaar?
- Eleve By Deyaar was 20% built at the site inspection on 24 September 2026. The site has been inspected 6 times since February 2024. The Land Department took 33 site photos at its inspections.
- Who is building Eleve By Deyaar?
- The registered developer is Deyaar Development. It has 8 other projects under construction in Dubai.
- Which bank holds the escrow account for Eleve By Deyaar?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Mar CasaAlso by Deyaar Development. 67%, Due October 2026, passed.
- Rosalia ResidencesAlso by Deyaar Development. 93%.
- Elm At Park FiveAlso by Deyaar Development. 16%, Due June 2027.
- Ember At Park FiveAlso by Deyaar Development. 18%, Due June 2027.
- Arian By AziziNearby in Down Town Jabal Ali. 2.0%, Due January 2028.
- Azizi AbrahamNearby in Down Town Jabal Ali. 2.0%, Due August 2027.
- Azizi WaresNearby in Down Town Jabal Ali. 2.0%, Due March 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)