Urbana II construction progress

The register lists Urbana II in Dubai World Central as complete, with a registered completion date of April 2020. Its last site inspection on record was in May 2020. The developer is Emaar Dubai South Dwc.

100%

Built, at the site inspection of 21 May 2020

Construction complete

Registered completion date
April 2020
Construction started
June 2017
First registered
February 2017
Units
236
Escrow bank
Commercial Bank of Dubai
Name in Arabic
Ii إربانا
Project number
1857
Site inspections
10

Schedule

The register lists Urbana II as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201820192020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

21 May 2020

100%+3.9 pts

  • Urbana II construction site, inspection photo 1, 21 May 2020
  • Urbana II construction site, inspection photo 2, 21 May 2020
  • Urbana II construction site, inspection photo 3, 21 May 2020
  • Urbana II construction site, inspection photo 4, 21 May 2020

30 December 2019

96%+2.0 pts

  • Urbana II construction site, inspection photo 1, 30 December 2019
  • Urbana II construction site, inspection photo 2, 30 December 2019
  • Urbana II construction site, inspection photo 3, 30 December 2019
  • Urbana II construction site, inspection photo 4, 30 December 2019

21 August 2019

94%+12 pts

  • Urbana II construction site, inspection photo 1, 21 August 2019
  • Urbana II construction site, inspection photo 2, 21 August 2019
  • Urbana II construction site, inspection photo 3, 21 August 2019
  • Urbana II construction site, inspection photo 4, 21 August 2019

7 March 2019

83%+11 pts

  • Urbana II construction site, inspection photo 1, 7 March 2019
  • Urbana II construction site, inspection photo 2, 7 March 2019
  • Urbana II construction site, inspection photo 3, 7 March 2019
  • Urbana II construction site, inspection photo 4, 7 March 2019

5 December 2018

71%+19 pts

  • Urbana II construction site, inspection photo 1, 5 December 2018
  • Urbana II construction site, inspection photo 2, 5 December 2018
  • Urbana II construction site, inspection photo 3, 5 December 2018
  • Urbana II construction site, inspection photo 4, 5 December 2018

9 September 2018

52%+7.0 pts

  • Urbana II construction site, inspection photo 1, 9 September 2018
  • Urbana II construction site, inspection photo 2, 9 September 2018
  • Urbana II construction site, inspection photo 3, 9 September 2018
  • Urbana II construction site, inspection photo 4, 9 September 2018

22 July 2018

45%+17 pts

  • Urbana II construction site, inspection photo 1, 22 July 2018
  • Urbana II construction site, inspection photo 2, 22 July 2018
  • Urbana II construction site, inspection photo 3, 22 July 2018
  • Urbana II construction site, inspection photo 4, 22 July 2018

11 April 2018

28%+11 pts

  • Urbana II construction site, inspection photo 1, 11 April 2018
  • Urbana II construction site, inspection photo 2, 11 April 2018
  • Urbana II construction site, inspection photo 3, 11 April 2018
  • Urbana II construction site, inspection photo 4, 11 April 2018

22 January 2018

17%+12 pts

  • Urbana II construction site, inspection photo 1, 22 January 2018
  • Urbana II construction site, inspection photo 2, 22 January 2018
  • Urbana II construction site, inspection photo 3, 22 January 2018
  • Urbana II construction site, inspection photo 4, 22 January 2018

17 September 2017

4.6%

  • Urbana II construction site, inspection photo 1, 17 September 2017
  • Urbana II construction site, inspection photo 2, 17 September 2017
  • Urbana II construction site, inspection photo 3, 17 September 2017
  • Urbana II construction site, inspection photo 4, 17 September 2017

All 96 site photos, by inspection date

Context

Dubai World Central has 53 projects under construction, 31% built on average.

Emaar Dubai South Dwc has 23 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Urbana II?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Urbana II handover date?
Construction of Urbana II is recorded as complete, with a registered completion date of April 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Urbana II?
Urbana II was 100% built at the site inspection on 21 May 2020. The site has been inspected 10 times since September 2017. The Land Department took 96 site photos at its inspections.
Is Urbana II delayed?
The register lists construction as complete.
Who is building Urbana II?
The registered developer is Emaar Dubai South Dwc. It has 23 other projects under construction in Dubai.
Which bank holds the escrow account for Urbana II?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.