Parkside 3 construction progress

The register lists Parkside 3 in Dubai World Central as complete, with a registered completion date of May 2022. Its last site inspection on record was in December 2022. The developer is Emaar Dubai South Dwc.

100%

Built, at the site inspection of 29 December 2022

Construction complete

Registered completion date
May 2022
Construction started
June 2019
First registered
May 2019
Units
365
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
بارك سايد 3
Project number
2148
Site inspections
9

Schedule

The register lists Parkside 3 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202020212022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

29 December 2022

100%+18 pts

  • Parkside 3 construction site, inspection photo 1, 29 December 2022
  • Parkside 3 construction site, inspection photo 2, 29 December 2022
  • Parkside 3 construction site, inspection photo 3, 29 December 2022
  • Parkside 3 construction site, inspection photo 4, 29 December 2022

30 August 2022

82%+19 pts

  • Parkside 3 construction site, inspection photo 1, 30 August 2022
  • Parkside 3 construction site, inspection photo 2, 30 August 2022
  • Parkside 3 construction site, inspection photo 3, 30 August 2022
  • Parkside 3 construction site, inspection photo 4, 30 August 2022

26 April 2022

63%+21 pts

  • Parkside 3 construction site, inspection photo 1, 26 April 2022
  • Parkside 3 construction site, inspection photo 2, 26 April 2022
  • Parkside 3 construction site, inspection photo 3, 26 April 2022
  • Parkside 3 construction site, inspection photo 4, 26 April 2022

29 November 2021

42%+6.8 pts

  • Parkside 3 construction site, inspection photo 1, 29 November 2021
  • Parkside 3 construction site, inspection photo 2, 29 November 2021
  • Parkside 3 construction site, inspection photo 3, 29 November 2021
  • Parkside 3 construction site, inspection photo 4, 29 November 2021

8 August 2021

35%+13 pts

  • Parkside 3 construction site, inspection photo 1, 8 August 2021
  • Parkside 3 construction site, inspection photo 2, 8 August 2021
  • Parkside 3 construction site, inspection photo 3, 8 August 2021
  • Parkside 3 construction site, inspection photo 4, 8 August 2021

18 April 2021

22%+9.3 pts

  • Parkside 3 construction site, inspection photo 1, 18 April 2021
  • Parkside 3 construction site, inspection photo 2, 18 April 2021
  • Parkside 3 construction site, inspection photo 3, 18 April 2021
  • Parkside 3 construction site, inspection photo 4, 18 April 2021

21 December 2020

13%+2.6 pts

  • Parkside 3 construction site, inspection photo 1, 21 December 2020
  • Parkside 3 construction site, inspection photo 2, 21 December 2020
  • Parkside 3 construction site, inspection photo 3, 21 December 2020
  • Parkside 3 construction site, inspection photo 4, 21 December 2020

11 March 2020

10%+8.4 pts

  • Parkside 3 construction site, inspection photo 1, 11 March 2020
  • Parkside 3 construction site, inspection photo 2, 11 March 2020
  • Parkside 3 construction site, inspection photo 3, 11 March 2020
  • Parkside 3 construction site, inspection photo 4, 11 March 2020

21 November 2019

1.7%

  • Parkside 3 construction site, inspection photo 1, 21 November 2019
  • Parkside 3 construction site, inspection photo 2, 21 November 2019
  • Parkside 3 construction site, inspection photo 3, 21 November 2019
  • Parkside 3 construction site, inspection photo 4, 21 November 2019

All 98 site photos, by inspection date

Context

Dubai World Central has 53 projects under construction, 31% built on average.

Emaar Dubai South Dwc has 23 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Parkside 3?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Parkside 3 handover date?
Construction of Parkside 3 is recorded as complete, with a registered completion date of May 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Parkside 3?
Parkside 3 was 100% built at the site inspection on 29 December 2022. The site has been inspected 9 times since November 2019. The Land Department took 98 site photos at its inspections.
Is Parkside 3 delayed?
The register lists construction as complete.
Who is building Parkside 3?
The registered developer is Emaar Dubai South Dwc. It has 23 other projects under construction in Dubai.
Which bank holds the escrow account for Parkside 3?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.