Golf Links construction progress

The register lists Golf Links in Dubai World Central as complete, with a registered completion date of May 2020. Its last site inspection on record was in June 2020. The developer is Emaar Dubai South Dwc.

100%

Built, at the site inspection of 18 June 2020

Construction complete

Registered completion date
May 2020
Construction started
October 2017
First registered
May 2017
Units
204
Escrow bank
Mashreq Bank
Name in Arabic
جولف لينكس
Project number
1900
Site inspections
10

Schedule

The register lists Golf Links as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201820192020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

18 June 2020

100%+4.8 pts

  • Golf Links construction site, inspection photo 1, 18 June 2020
  • Golf Links construction site, inspection photo 2, 18 June 2020
  • Golf Links construction site, inspection photo 3, 18 June 2020
  • Golf Links construction site, inspection photo 4, 18 June 2020

14 April 2020

95%+14 pts

  • Golf Links construction site, inspection photo 1, 14 April 2020
  • Golf Links construction site, inspection photo 2, 14 April 2020
  • Golf Links construction site, inspection photo 3, 14 April 2020
  • Golf Links construction site, inspection photo 4, 14 April 2020

25 December 2019

82%+6.8 pts

  • Golf Links construction site, inspection photo 1, 25 December 2019
  • Golf Links construction site, inspection photo 2, 25 December 2019
  • Golf Links construction site, inspection photo 3, 25 December 2019
  • Golf Links construction site, inspection photo 4, 25 December 2019

12 November 2019

75%+13 pts

  • Golf Links construction site, inspection photo 1, 12 November 2019
  • Golf Links construction site, inspection photo 2, 12 November 2019
  • Golf Links construction site, inspection photo 3, 12 November 2019
  • Golf Links construction site, inspection photo 4, 12 November 2019

20 August 2019

62%+22 pts

  • Golf Links construction site, inspection photo 1, 20 August 2019
  • Golf Links construction site, inspection photo 2, 20 August 2019
  • Golf Links construction site, inspection photo 3, 20 August 2019
  • Golf Links construction site, inspection photo 4, 20 August 2019

31 March 2019

40%+17 pts

  • Golf Links construction site, inspection photo 1, 31 March 2019
  • Golf Links construction site, inspection photo 2, 31 March 2019
  • Golf Links construction site, inspection photo 3, 31 March 2019
  • Golf Links construction site, inspection photo 4, 31 March 2019

25 December 2018

23%+13 pts

  • Golf Links construction site, inspection photo 1, 25 December 2018
  • Golf Links construction site, inspection photo 2, 25 December 2018
  • Golf Links construction site, inspection photo 3, 25 December 2018
  • Golf Links construction site, inspection photo 4, 25 December 2018

9 September 2018

10%+7.0 pts

  • Golf Links construction site, inspection photo 1, 9 September 2018
  • Golf Links construction site, inspection photo 2, 9 September 2018
  • Golf Links construction site, inspection photo 3, 9 September 2018
  • Golf Links construction site, inspection photo 4, 9 September 2018

1 May 2018

3.1%+2.0 pts

  • Golf Links construction site, inspection photo 1, 1 May 2018
  • Golf Links construction site, inspection photo 2, 1 May 2018
  • Golf Links construction site, inspection photo 3, 1 May 2018
  • Golf Links construction site, inspection photo 4, 1 May 2018

22 January 2018

1.1%

  • Golf Links construction site, inspection photo 1, 22 January 2018
  • Golf Links construction site, inspection photo 2, 22 January 2018
  • Golf Links construction site, inspection photo 3, 22 January 2018
  • Golf Links construction site, inspection photo 4, 22 January 2018

All 100 site photos, by inspection date

Context

Dubai World Central has 53 projects under construction, 31% built on average.

Emaar Dubai South Dwc has 23 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Golf Links?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Golf Links handover date?
Construction of Golf Links is recorded as complete, with a registered completion date of May 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Golf Links?
Golf Links was 100% built at the site inspection on 18 June 2020. The site has been inspected 10 times since January 2018. The Land Department took 100 site photos at its inspections.
Is Golf Links delayed?
The register lists construction as complete.
Who is building Golf Links?
The registered developer is Emaar Dubai South Dwc. It has 23 other projects under construction in Dubai.
Which bank holds the escrow account for Golf Links?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.