Fairway Villas construction progress

The register lists Fairway Villas in Dubai World Central as complete, with a registered completion date of September 2025. Its last site inspection on record was in October 2025. The developer is Emaar Dubai South Dwc.

100%

Built, at the site inspection of 7 October 2025

Construction complete

Registered completion date
September 2025
Construction started
May 2023
First registered
December 2022
Units
49
Escrow bank
Dubai Islamic Bank
Name in Arabic
فيرواي فيلاز
Project number
2519
Site inspections
9

Schedule

The register lists Fairway Villas as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202320242025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

7 October 2025

100%+15 pts

  • Fairway Villas construction site, inspection photo 1, 7 October 2025
  • Fairway Villas construction site, inspection photo 2, 7 October 2025
  • Fairway Villas construction site, inspection photo 3, 7 October 2025
  • Fairway Villas construction site, inspection photo 4, 7 October 2025

18 July 2025

85%+23 pts

  • Fairway Villas construction site, inspection photo 1, 18 July 2025
  • Fairway Villas construction site, inspection photo 2, 18 July 2025
  • Fairway Villas construction site, inspection photo 3, 18 July 2025
  • Fairway Villas construction site, inspection photo 4, 18 July 2025

30 April 2025

62%+18 pts

  • Fairway Villas construction site, inspection photo 1, 30 April 2025
  • Fairway Villas construction site, inspection photo 2, 30 April 2025
  • Fairway Villas construction site, inspection photo 3, 30 April 2025
  • Fairway Villas construction site, inspection photo 4, 30 April 2025

21 January 2025

44%+20 pts

  • Fairway Villas construction site, inspection photo 1, 21 January 2025
  • Fairway Villas construction site, inspection photo 2, 21 January 2025
  • Fairway Villas construction site, inspection photo 3, 21 January 2025
  • Fairway Villas construction site, inspection photo 4, 21 January 2025

20 September 2024

24%+22 pts

  • Fairway Villas construction site, inspection photo 1, 20 September 2024
  • Fairway Villas construction site, inspection photo 2, 20 September 2024
  • Fairway Villas construction site, inspection photo 3, 20 September 2024
  • Fairway Villas construction site, inspection photo 4, 20 September 2024

25 March 2024

1.9%+0.7 pts

  • Fairway Villas construction site, inspection photo 1, 25 March 2024
  • Fairway Villas construction site, inspection photo 2, 25 March 2024
  • Fairway Villas construction site, inspection photo 3, 25 March 2024

28 September 2023

1.1%+1.1 pts

  • Fairway Villas construction site, inspection photo 1, 28 September 2023
  • Fairway Villas construction site, inspection photo 2, 28 September 2023
  • Fairway Villas construction site, inspection photo 3, 28 September 2023
  • Fairway Villas construction site, inspection photo 4, 28 September 2023

1 June 2023

0.1%+0.1 pts

  • Fairway Villas construction site, inspection photo 1, 1 June 2023
  • Fairway Villas construction site, inspection photo 2, 1 June 2023

28 November 2022

0%

  • Fairway Villas construction site, inspection photo 1, 28 November 2022
  • Fairway Villas construction site, inspection photo 2, 28 November 2022

All 50 site photos, by inspection date

Context

Dubai World Central has 53 projects under construction, 31% built on average.

Emaar Dubai South Dwc has 23 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Fairway Villas?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Fairway Villas handover date?
Construction of Fairway Villas is recorded as complete, with a registered completion date of September 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Fairway Villas?
Fairway Villas was 100% built at the site inspection on 7 October 2025. The site has been inspected 9 times since November 2022. The Land Department took 50 site photos at its inspections.
Is Fairway Villas delayed?
The register lists construction as complete.
Who is building Fairway Villas?
The registered developer is Emaar Dubai South Dwc. It has 23 other projects under construction in Dubai.
Which bank holds the escrow account for Fairway Villas?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.