Azizi Venice 1 construction photos
39 photos from 6 site inspections, newest first. The percentage is how much of Azizi Venice 1 was built on the day of each visit.
13 May 202667% built
29 January 202661% built
21 July 202552% built
10 April 202548% built
10 September 202423% built
25 October 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.