Azizi Grand construction photos

62 photos from 8 site inspections, newest first. The percentage is how much of Azizi Grand was built on the day of each visit.

24 June 202682% built

29 January 202675% built

21 October 202557% built

3 June 202548% built

6 February 202526% built

8 October 202412% built

25 July 20248.8% built

11 September 20230% built

Back to Azizi Grand construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.