Design Quarter construction progress
Design Quarter in Business Park is 41% built at the Land Department inspection of September 2026. Developer Dhre 2 Bts. Completion registered for February 2027.
41%
Built, at the Land Department site inspection of 28 September 2026
Running behind its date
- Completion date (Land Department)
- February 2027
- Finish at recent pace
- December 2028
- Construction started
- May 2023
- Registered with the Land Department
- March 2023
- Developer
- Dhre 2 Bts
- Community
- Business Park
- Units
- 564
- Escrow bank
- Emirates NBD
- Name in Arabic
- ديزاين كوارتر
- Land Department project number
- 2607
- Land Department site inspections
- 9
Schedule
Between November 2025 and September 2026 the site added about 2.2 points a month. At that rate it would finish around December 2028, more than three months after the February 2027 date registered with the Land Department.
Site inspections
28 September 2026
41%+9.8 pts
30 June 2026
31%+4.7 pts
26 March 2026
26%+9.4 pts
7 November 2025
17%+3.3 pts
30 July 2025
14%+5.1 pts
2 May 2025
8.5%+3.7 pts
7 February 2025
4.8%+1.7 pts
3 June 2024
3.1%+2.2 pts
8 March 2023
0.9%
Context
Business Park has 2 projects under construction, 21% built on average.
Dhre 2 Bts has 11 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Design Quarter?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Design Quarter be completed?
- The completion date registered with the Dubai Land Department is February 2027. At the pace of its recent inspections the site would reach 100% around December 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Design Quarter is built?
- 41%, measured at the Land Department site inspection on 28 September 2026. The Land Department engineers have inspected the site 9 times since March 2023.
- Is Design Quarter delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2027.
- Who is building Design Quarter?
- The registered developer is Dhre 2 Bts. It has 10 other projects under construction in Dubai.
- Which bank holds the escrow account for Design Quarter?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Bulgari Lighthouse DubaiAlso by Dhre 2 Bts. 64%, Due March 2027.
- Bluewaters BayAlso by Dhre 2 Bts. 37%, Due March 2027.
- The AcresAlso by Dhre 2 Bts. 25%.
- The Acres 3 & EstatesAlso by Dhre 2 Bts. 15%, Due November 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.