Skip to content

Design Quarter construction progress

Design Quarter in Business Park is 41% built at the Land Department inspection of September 2026. Developer Dhre 2 Bts. Completion registered for February 2027.

41%

Built, at the Land Department site inspection of 28 September 2026

Running behind its date

Completion date (Land Department)
February 2027
Finish at recent pace
December 2028
Construction started
May 2023
Registered with the Land Department
March 2023
Developer
Dhre 2 Bts
Community
Business Park
Units
564
Escrow bank
Emirates NBD
Name in Arabic
ديزاين كوارتر
Land Department project number
2607
Land Department site inspections
9

Schedule

Between November 2025 and September 2026 the site added about 2.2 points a month. At that rate it would finish around December 2028, more than three months after the February 2027 date registered with the Land Department.

0%25%50%75%100%2024202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

28 September 2026

41%+9.8 pts

  • Design Quarter construction site, Land Department inspection photo 1, 28 September 2026
  • Design Quarter construction site, Land Department inspection photo 2, 28 September 2026
  • Design Quarter construction site, Land Department inspection photo 3, 28 September 2026
  • Design Quarter construction site, Land Department inspection photo 4, 28 September 2026

30 June 2026

31%+4.7 pts

  • Design Quarter construction site, Land Department inspection photo 1, 30 June 2026
  • Design Quarter construction site, Land Department inspection photo 2, 30 June 2026
  • Design Quarter construction site, Land Department inspection photo 3, 30 June 2026
  • Design Quarter construction site, Land Department inspection photo 4, 30 June 2026

26 March 2026

26%+9.4 pts

  • Design Quarter construction site, Land Department inspection photo 1, 26 March 2026
  • Design Quarter construction site, Land Department inspection photo 2, 26 March 2026
  • Design Quarter construction site, Land Department inspection photo 3, 26 March 2026
  • Design Quarter construction site, Land Department inspection photo 4, 26 March 2026

7 November 2025

17%+3.3 pts

  • Design Quarter construction site, Land Department inspection photo 1, 7 November 2025
  • Design Quarter construction site, Land Department inspection photo 2, 7 November 2025
  • Design Quarter construction site, Land Department inspection photo 3, 7 November 2025
  • Design Quarter construction site, Land Department inspection photo 4, 7 November 2025

30 July 2025

14%+5.1 pts

  • Design Quarter construction site, Land Department inspection photo 1, 30 July 2025
  • Design Quarter construction site, Land Department inspection photo 2, 30 July 2025
  • Design Quarter construction site, Land Department inspection photo 3, 30 July 2025
  • Design Quarter construction site, Land Department inspection photo 4, 30 July 2025

2 May 2025

8.5%+3.7 pts

  • Design Quarter construction site, Land Department inspection photo 1, 2 May 2025
  • Design Quarter construction site, Land Department inspection photo 2, 2 May 2025
  • Design Quarter construction site, Land Department inspection photo 3, 2 May 2025
  • Design Quarter construction site, Land Department inspection photo 4, 2 May 2025

7 February 2025

4.8%+1.7 pts

  • Design Quarter construction site, Land Department inspection photo 1, 7 February 2025
  • Design Quarter construction site, Land Department inspection photo 2, 7 February 2025
  • Design Quarter construction site, Land Department inspection photo 3, 7 February 2025
  • Design Quarter construction site, Land Department inspection photo 4, 7 February 2025

3 June 2024

3.1%+2.2 pts

  • Design Quarter construction site, Land Department inspection photo 1, 3 June 2024
  • Design Quarter construction site, Land Department inspection photo 2, 3 June 2024

8 March 2023

0.9%

  • Design Quarter construction site, Land Department inspection photo 1, 8 March 2023
  • Design Quarter construction site, Land Department inspection photo 2, 8 March 2023
  • Design Quarter construction site, Land Department inspection photo 3, 8 March 2023

All 70 site photos, by inspection date

Context

Business Park has 2 projects under construction, 21% built on average.

Dhre 2 Bts has 11 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Design Quarter?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Design Quarter be completed?
The completion date registered with the Dubai Land Department is February 2027. At the pace of its recent inspections the site would reach 100% around December 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Design Quarter is built?
41%, measured at the Land Department site inspection on 28 September 2026. The Land Department engineers have inspected the site 9 times since March 2023.
Is Design Quarter delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2027.
Who is building Design Quarter?
The registered developer is Dhre 2 Bts. It has 10 other projects under construction in Dubai.
Which bank holds the escrow account for Design Quarter?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.