Bluewaters Bay construction photos
70 photos taken by Dubai Land Department engineers at 11 site inspections, newest first. The percentage is how much of Bluewaters Bay was built on the day of each visit.
25 August 202637% built
27 April 202628% built
26 January 202622% built
7 October 202516% built
7 July 202513% built
18 April 202510% built
16 January 20257.4% built
23 September 20242.0% built
21 March 20241.9% built
9 August 20230.9% built
28 November 20220% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.