Bluewaters Bay construction photos

70 photos from 11 site inspections, newest first. The percentage is how much of Bluewaters Bay was built on the day of each visit.

25 August 202637% built

27 April 202628% built

26 January 202622% built

7 October 202516% built

7 July 202513% built

18 April 202510% built

16 January 20257.4% built

23 September 20242.0% built

21 March 20241.9% built

9 August 20230.9% built

28 November 20220% built

Back to Bluewaters Bay construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.