The Acres construction progress

No completion date is registered for The Acres in Wadi Al Safa 7 yet. At the last site inspection, in August 2026, it was 25% built. The developer is Dhre 2 Bts.

38%

Built, at the site inspection of 20 August 2026

Finish at recent pace
April 2029
Construction started
September 2024
First registered
April 2024
Developer
Dhre 2 Bts
Units
642
Escrow bank
Dubai Islamic Bank
Name in Arabic
ذا إيكرز
Project number
3019
Site inspections
8

Schedule

Since October 2025 The Acres has added about 2.4 points a month. At that rate the site reaches 100% around April 2029. No completion date is on record to compare it with.

0%25%50%75%100%20252026
Progress at each site inspection

Site inspections

20 August 2026

25%+10 pts

  • The Acres construction site, inspection photo 1, 20 August 2026
  • The Acres construction site, inspection photo 2, 20 August 2026
  • The Acres construction site, inspection photo 3, 20 August 2026
  • The Acres construction site, inspection photo 4, 20 August 2026

14 May 2026

15%+5.7 pts

  • The Acres construction site, inspection photo 1, 14 May 2026
  • The Acres construction site, inspection photo 2, 14 May 2026
  • The Acres construction site, inspection photo 3, 14 May 2026
  • The Acres construction site, inspection photo 4, 14 May 2026

23 February 2026

9.1%+7.4 pts

  • The Acres construction site, inspection photo 1, 23 February 2026
  • The Acres construction site, inspection photo 2, 23 February 2026
  • The Acres construction site, inspection photo 3, 23 February 2026
  • The Acres construction site, inspection photo 4, 23 February 2026

11 November 2025

1.6%+1.3 pts

  • The Acres construction site, inspection photo 1, 11 November 2025
  • The Acres construction site, inspection photo 2, 11 November 2025
  • The Acres construction site, inspection photo 3, 11 November 2025
  • The Acres construction site, inspection photo 4, 11 November 2025

3 October 2025

0.3%+0.1 pts

  • The Acres construction site, inspection photo 1, 3 October 2025
  • The Acres construction site, inspection photo 2, 3 October 2025
  • The Acres construction site, inspection photo 3, 3 October 2025
  • The Acres construction site, inspection photo 4, 3 October 2025

7 April 2025

0.3%+0.0 pts

  • The Acres construction site, inspection photo 1, 7 April 2025
  • The Acres construction site, inspection photo 2, 7 April 2025
  • The Acres construction site, inspection photo 3, 7 April 2025

25 November 2024

0.2%+0.2 pts

  • The Acres construction site, inspection photo 1, 25 November 2024
  • The Acres construction site, inspection photo 2, 25 November 2024
  • The Acres construction site, inspection photo 3, 25 November 2024
  • The Acres construction site, inspection photo 4, 25 November 2024

27 March 2024

0%

  • The Acres construction site, inspection photo 1, 27 March 2024
  • The Acres construction site, inspection photo 2, 27 March 2024
  • The Acres construction site, inspection photo 3, 27 March 2024
  • The Acres construction site, inspection photo 4, 27 March 2024

All 61 site photos, by inspection date

Context

Wadi Al Safa 7 has 4 projects under construction, 24% built on average.

Dhre 2 Bts has 12 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Acres?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Acres handover date?
No completion date is on record for The Acres yet. Handover follows completion, so there is no date to give.
What is the latest construction update on The Acres?
The Acres was 38% built at the site inspection on 20 August 2026. The site has been inspected 8 times since March 2024. The Land Department took 61 site photos at its inspections.
Who is building The Acres?
The registered developer is Dhre 2 Bts. It has 11 other projects under construction in Dubai.
Which bank holds the escrow account for The Acres?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.