The Acres 3 & Estates construction progress

The Acres 3 & Estates in Wadi Al Safa 7 is 15% built at the Land Department inspection of September 2026. Developer Dhre 2 Bts. Completion registered for November 2027.

15%

Built, at the Land Department site inspection of 30 September 2026

Running behind its date

Completion date (Land Department)
November 2027
Finish at recent pace
September 2032
Construction started
November 2024
Registered with the Land Department
September 2024
Developer
Dhre 2 Bts
Units
291
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
ذا إيكرز 3 آند إستيتس
Land Department project number
3126
Land Department site inspections
8

Schedule

Between October 2025 and September 2026 the site added about 1.2 points a month. At that rate it would finish around September 2032, more than three months after the November 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

30 September 2026

15%+9.7 pts

  • The Acres 3 & Estates construction site, Land Department inspection photo 1, 30 September 2026
  • The Acres 3 & Estates construction site, Land Department inspection photo 2, 30 September 2026
  • The Acres 3 & Estates construction site, Land Department inspection photo 3, 30 September 2026
  • The Acres 3 & Estates construction site, Land Department inspection photo 4, 30 September 2026

24 June 2026

5.1%+4.4 pts

  • The Acres 3 & Estates construction site, Land Department inspection photo 1, 24 June 2026
  • The Acres 3 & Estates construction site, Land Department inspection photo 2, 24 June 2026
  • The Acres 3 & Estates construction site, Land Department inspection photo 3, 24 June 2026
  • The Acres 3 & Estates construction site, Land Department inspection photo 4, 24 June 2026

16 March 2026

0.7%

  • The Acres 3 & Estates construction site, Land Department inspection photo 1, 16 March 2026
  • The Acres 3 & Estates construction site, Land Department inspection photo 2, 16 March 2026
  • The Acres 3 & Estates construction site, Land Department inspection photo 3, 16 March 2026

31 December 2025

0.7%

  • The Acres 3 & Estates construction site, Land Department inspection photo 1, 31 December 2025
  • The Acres 3 & Estates construction site, Land Department inspection photo 2, 31 December 2025

2 October 2025

0.7%

  • The Acres 3 & Estates construction site, Land Department inspection photo 1, 2 October 2025
  • The Acres 3 & Estates construction site, Land Department inspection photo 2, 2 October 2025
  • The Acres 3 & Estates construction site, Land Department inspection photo 3, 2 October 2025
  • The Acres 3 & Estates construction site, Land Department inspection photo 4, 2 October 2025

7 July 2025

0.7%+0.5 pts

  • The Acres 3 & Estates construction site, Land Department inspection photo 1, 7 July 2025
  • The Acres 3 & Estates construction site, Land Department inspection photo 2, 7 July 2025
  • The Acres 3 & Estates construction site, Land Department inspection photo 3, 7 July 2025
  • The Acres 3 & Estates construction site, Land Department inspection photo 4, 7 July 2025

7 April 2025

0.3%+0.3 pts

  • The Acres 3 & Estates construction site, Land Department inspection photo 1, 7 April 2025
  • The Acres 3 & Estates construction site, Land Department inspection photo 2, 7 April 2025
  • The Acres 3 & Estates construction site, Land Department inspection photo 3, 7 April 2025
  • The Acres 3 & Estates construction site, Land Department inspection photo 4, 7 April 2025

3 June 2024

0%

  • The Acres 3 & Estates construction site, Land Department inspection photo 1, 3 June 2024
  • The Acres 3 & Estates construction site, Land Department inspection photo 2, 3 June 2024

All 42 site photos, by inspection date

Context

Wadi Al Safa 7 has 4 projects under construction, 20% built on average.

Dhre 2 Bts has 11 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Acres 3 & Estates?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will The Acres 3 & Estates be completed?
The completion date registered with the Dubai Land Department is November 2027. At the pace of its recent inspections the site would reach 100% around September 2032. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Acres 3 & Estates is built?
15%, measured at the Land Department site inspection on 30 September 2026. The Land Department engineers have inspected the site 8 times since June 2024.
Is The Acres 3 & Estates delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
Who is building The Acres 3 & Estates?
The registered developer is Dhre 2 Bts. It has 10 other projects under construction in Dubai.
Which bank holds the escrow account for The Acres 3 & Estates?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.