The Acres 3 & Estates construction progress
The Acres 3 & Estates in Wadi Al Safa 7 is 15% built at the Land Department inspection of September 2026. Developer Dhre 2 Bts. Completion registered for November 2027.
15%
Built, at the Land Department site inspection of 30 September 2026
Running behind its date
- Completion date (Land Department)
- November 2027
- Finish at recent pace
- September 2032
- Construction started
- November 2024
- Registered with the Land Department
- September 2024
- Developer
- Dhre 2 Bts
- Community
- Wadi Al Safa 7
- Units
- 291
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- ذا إيكرز 3 آند إستيتس
- Land Department project number
- 3126
- Land Department site inspections
- 8
Schedule
Between October 2025 and September 2026 the site added about 1.2 points a month. At that rate it would finish around September 2032, more than three months after the November 2027 date registered with the Land Department.
Site inspections
30 September 2026
15%+9.7 pts
24 June 2026
5.1%+4.4 pts
16 March 2026
0.7%
31 December 2025
0.7%
2 October 2025
0.7%
7 July 2025
0.7%+0.5 pts
7 April 2025
0.3%+0.3 pts
3 June 2024
0%
Context
Wadi Al Safa 7 has 4 projects under construction, 20% built on average.
Dhre 2 Bts has 11 projects under construction in Dubai, none past their registered completion dates.
Own a unit in The Acres 3 & Estates?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will The Acres 3 & Estates be completed?
- The completion date registered with the Dubai Land Department is November 2027. At the pace of its recent inspections the site would reach 100% around September 2032. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of The Acres 3 & Estates is built?
- 15%, measured at the Land Department site inspection on 30 September 2026. The Land Department engineers have inspected the site 8 times since June 2024.
- Is The Acres 3 & Estates delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
- Who is building The Acres 3 & Estates?
- The registered developer is Dhre 2 Bts. It has 10 other projects under construction in Dubai.
- Which bank holds the escrow account for The Acres 3 & Estates?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Bulgari Lighthouse DubaiAlso by Dhre 2 Bts. 64%, Due March 2027.
- Bluewaters BayAlso by Dhre 2 Bts. 37%, Due March 2027.
- Design QuarterAlso by Dhre 2 Bts. 41%, Due February 2027.
- The AcresAlso by Dhre 2 Bts. 25%.
- Reportage Village 1Nearby in Wadi Al Safa 7. 25%, Due December 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


.png&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.png&w=3840&q=75)
.jpg&w=3840&q=75)