Bulgari Lighthouse Dubai construction progress
The registered completion date for Bulgari Lighthouse Dubai in Jumeira Bay is March 2027. At the last site inspection, in October 2026, it was 80% built. The developer is Dhre 2 Bts.
80%
Built, at the site inspection of 8 October 2026
On pace for its date
- Registered completion date
- March 2027
- Finish at recent pace
- March 2027
- Construction started
- February 2023
- First registered
- November 2022
- Developer
- Dhre 2 Bts
- Community
- Jumeira Bay
- Units
- 31
- Escrow bank
- Commercial Bank of Dubai
- Name in Arabic
- بولغري لايتهاوس دبي
- Project number
- 2507
- Site inspections
- 12
Schedule
Since October 2025 Bulgari Lighthouse Dubai has added about 3.7 points a month. That puts 100% around March 2027, within three months of its registered completion date of March 2027.
Site inspections
8 October 2026
80%+16 pts
9 July 2026
64%+10 pts
15 April 2026
53%+9.6 pts
15 January 2026
44%+7.5 pts
15 October 2025
36%+13 pts
25 July 2025
23%+3.8 pts
30 April 2025
19%+4.7 pts
16 January 2025
15%+6.1 pts
20 September 2024
8.6%+7.2 pts
1 April 2024
1.4%+1.3 pts
Context
Dhre 2 Bts has 12 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Bulgari Lighthouse Dubai?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Bulgari Lighthouse Dubai handover date?
- The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Bulgari Lighthouse Dubai?
- Bulgari Lighthouse Dubai was 80% built at the site inspection on 8 October 2026. The site has been inspected 12 times since November 2022. The Land Department took 81 site photos at its inspections.
- Is Bulgari Lighthouse Dubai delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of March 2027.
- Who is building Bulgari Lighthouse Dubai?
- The registered developer is Dhre 2 Bts. It has 11 other projects under construction in Dubai.
- Which bank holds the escrow account for Bulgari Lighthouse Dubai?
- Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Bluewaters BayAlso by Dhre 2 Bts. 37%, Due March 2027.
- Design QuarterAlso by Dhre 2 Bts. 41%, Due February 2027.
- The AcresAlso by Dhre 2 Bts. 38%.
- The Acres 3 & EstatesAlso by Dhre 2 Bts. 15%, Due November 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.



.png&w=3840&q=75)








.jpeg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)