5242 construction progress

The register lists 5242 in Dubai Marina as complete, with a registered completion date of September 2020. Its last site inspection on record was in April 2021. The developer is Emaar Development.

100%

Built, at the site inspection of 27 April 2021

Construction complete

Registered completion date
September 2020
Construction started
October 2016
First registered
April 2016
Community
Dubai Marina
Units
493
Escrow bank
Dubai Islamic Bank
Name in Arabic
5242
Project number
1747
Site inspections
17

Schedule

The register lists 5242 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20172018201920202021
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

27 April 2021

100%+3.3 pts

  • 5242 construction site, inspection photo 1, 27 April 2021
  • 5242 construction site, inspection photo 2, 27 April 2021
  • 5242 construction site, inspection photo 3, 27 April 2021
  • 5242 construction site, inspection photo 4, 27 April 2021

18 March 2021

97%+1.3 pts

  • 5242 construction site, inspection photo 1, 18 March 2021
  • 5242 construction site, inspection photo 2, 18 March 2021
  • 5242 construction site, inspection photo 3, 18 March 2021
  • 5242 construction site, inspection photo 4, 18 March 2021

19 January 2021

95%+2.1 pts

  • 5242 construction site, inspection photo 1, 19 January 2021
  • 5242 construction site, inspection photo 2, 19 January 2021
  • 5242 construction site, inspection photo 3, 19 January 2021
  • 5242 construction site, inspection photo 4, 19 January 2021

23 September 2020

93%+3.3 pts

  • 5242 construction site, inspection photo 1, 23 September 2020
  • 5242 construction site, inspection photo 2, 23 September 2020
  • 5242 construction site, inspection photo 3, 23 September 2020
  • 5242 construction site, inspection photo 4, 23 September 2020

15 June 2020

90%+4.0 pts

  • 5242 construction site, inspection photo 1, 15 June 2020
  • 5242 construction site, inspection photo 2, 15 June 2020
  • 5242 construction site, inspection photo 3, 15 June 2020
  • 5242 construction site, inspection photo 4, 15 June 2020

10 March 2020

86%+6.0 pts

  • 5242 construction site, inspection photo 1, 10 March 2020
  • 5242 construction site, inspection photo 2, 10 March 2020
  • 5242 construction site, inspection photo 3, 10 March 2020
  • 5242 construction site, inspection photo 4, 10 March 2020

11 November 2019

80%+13 pts

  • 5242 construction site, inspection photo 1, 11 November 2019
  • 5242 construction site, inspection photo 2, 11 November 2019
  • 5242 construction site, inspection photo 3, 11 November 2019
  • 5242 construction site, inspection photo 4, 11 November 2019

3 July 2019

67%+14 pts

  • 5242 construction site, inspection photo 1, 3 July 2019
  • 5242 construction site, inspection photo 2, 3 July 2019
  • 5242 construction site, inspection photo 3, 3 July 2019
  • 5242 construction site, inspection photo 4, 3 July 2019

26 February 2019

53%+6.6 pts

  • 5242 construction site, inspection photo 1, 26 February 2019
  • 5242 construction site, inspection photo 2, 26 February 2019
  • 5242 construction site, inspection photo 3, 26 February 2019
  • 5242 construction site, inspection photo 4, 26 February 2019

2 January 2019

46%+11 pts

  • 5242 construction site, inspection photo 1, 2 January 2019
  • 5242 construction site, inspection photo 2, 2 January 2019
  • 5242 construction site, inspection photo 3, 2 January 2019
  • 5242 construction site, inspection photo 4, 2 January 2019

All 160 site photos, by inspection date

Context

Dubai Marina has 13 projects under construction, 46% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in 5242?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the 5242 handover date?
Construction of 5242 is recorded as complete, with a registered completion date of September 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on 5242?
5242 was 100% built at the site inspection on 27 April 2021. The site has been inspected 17 times since December 2016. The Land Department took 160 site photos at its inspections.
Is 5242 delayed?
The register lists construction as complete.
Who is building 5242?
The registered developer is Emaar Development. It has 52 other projects under construction in Dubai.
Which bank holds the escrow account for 5242?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.