Address The Bay construction progress
Address The Bay in Dubai Harbour is 70% built at the Land Department inspection of July 2026. Developer Emaar Development. Completion registered for December 2026.
70%
Built, at the Land Department site inspection of 15 July 2026
Running behind its date
- Completion date (Land Department)
- December 2026
- Finish at recent pace
- June 2027
- Construction started
- November 2022
- Registered with the Land Department
- June 2022
- Developer
- Emaar Development
- Community
- Dubai Harbour
- Units
- 448
- Escrow bank
- Commercial Bank of Dubai
- Name in Arabic
- العنوان ذا باي
- Land Department project number
- 2397
- Land Department site inspections
- 11
Schedule
Between December 2025 and July 2026 the site added about 2.8 points a month. At that rate it would finish around June 2027, more than three months after the December 2026 date registered with the Land Department.
Site inspections
15 July 2026
70%+3.0 pts
17 March 2026
67%+18 pts
4 December 2025
49%+10 pts
10 July 2025
39%+9.6 pts
28 April 2025
30%+9.0 pts
16 December 2024
21%+8.3 pts
23 August 2024
12%+5.5 pts
21 March 2024
6.9%+5.5 pts
9 October 2023
1.4%+1.4 pts
20 June 2023
0%+0.0 pts
Context
Dubai Harbour has 11 projects under construction, 35% built on average. Address The Bay is ahead of that average.
Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Address The Bay?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Address The Bay be completed?
- The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around June 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Address The Bay is built?
- 70%, measured at the Land Department site inspection on 15 July 2026. The Land Department engineers have inspected the site 11 times since March 2023.
- Is Address The Bay delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Address The Bay?
- The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
- Which bank holds the escrow account for Address The Bay?
- Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The St. Regis Residences, Downtown DubaiAlso by Emaar Development. 76%, Due December 2026.
- SeapointAlso by Emaar Development. 37%, Due March 2028.
- BayviewAlso by Emaar Development. 63%, Due July 2028.
- The Valley - RivanaAlso by Emaar Development. 94%, Due March 2027.
- Sobha Seahaven Tower ANearby in Dubai Harbour. 37%, Due April 2028.
- Damac BayNearby in Dubai Harbour. 34%, Due January 2027.
- Damac Bay 2Nearby in Dubai Harbour. 30%.
- Sobha Seahaven Tower B & CNearby in Dubai Harbour. 40%, Due October 2028.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.