Address The Bay construction progress

Address The Bay in Dubai Harbour is 70% built at the Land Department inspection of July 2026. Developer Emaar Development. Completion registered for December 2026.

70%

Built, at the Land Department site inspection of 15 July 2026

Running behind its date

Completion date (Land Department)
December 2026
Finish at recent pace
June 2027
Construction started
November 2022
Registered with the Land Department
June 2022
Community
Dubai Harbour
Units
448
Escrow bank
Commercial Bank of Dubai
Name in Arabic
العنوان ذا باي
Land Department project number
2397
Land Department site inspections
11

Schedule

Between December 2025 and July 2026 the site added about 2.8 points a month. At that rate it would finish around June 2027, more than three months after the December 2026 date registered with the Land Department.

0%25%50%75%100%2023202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

15 July 2026

70%+3.0 pts

  • Address The Bay construction site, Land Department inspection photo 1, 15 July 2026
  • Address The Bay construction site, Land Department inspection photo 2, 15 July 2026
  • Address The Bay construction site, Land Department inspection photo 3, 15 July 2026
  • Address The Bay construction site, Land Department inspection photo 4, 15 July 2026

17 March 2026

67%+18 pts

  • Address The Bay construction site, Land Department inspection photo 1, 17 March 2026
  • Address The Bay construction site, Land Department inspection photo 2, 17 March 2026
  • Address The Bay construction site, Land Department inspection photo 3, 17 March 2026
  • Address The Bay construction site, Land Department inspection photo 4, 17 March 2026

4 December 2025

49%+10 pts

  • Address The Bay construction site, Land Department inspection photo 1, 4 December 2025
  • Address The Bay construction site, Land Department inspection photo 2, 4 December 2025
  • Address The Bay construction site, Land Department inspection photo 3, 4 December 2025
  • Address The Bay construction site, Land Department inspection photo 4, 4 December 2025

10 July 2025

39%+9.6 pts

  • Address The Bay construction site, Land Department inspection photo 1, 10 July 2025
  • Address The Bay construction site, Land Department inspection photo 2, 10 July 2025
  • Address The Bay construction site, Land Department inspection photo 3, 10 July 2025
  • Address The Bay construction site, Land Department inspection photo 4, 10 July 2025

28 April 2025

30%+9.0 pts

  • Address The Bay construction site, Land Department inspection photo 1, 28 April 2025
  • Address The Bay construction site, Land Department inspection photo 2, 28 April 2025
  • Address The Bay construction site, Land Department inspection photo 3, 28 April 2025
  • Address The Bay construction site, Land Department inspection photo 4, 28 April 2025

16 December 2024

21%+8.3 pts

  • Address The Bay construction site, Land Department inspection photo 1, 16 December 2024
  • Address The Bay construction site, Land Department inspection photo 2, 16 December 2024
  • Address The Bay construction site, Land Department inspection photo 3, 16 December 2024
  • Address The Bay construction site, Land Department inspection photo 4, 16 December 2024

23 August 2024

12%+5.5 pts

  • Address The Bay construction site, Land Department inspection photo 1, 23 August 2024
  • Address The Bay construction site, Land Department inspection photo 2, 23 August 2024
  • Address The Bay construction site, Land Department inspection photo 3, 23 August 2024
  • Address The Bay construction site, Land Department inspection photo 4, 23 August 2024

21 March 2024

6.9%+5.5 pts

  • Address The Bay construction site, Land Department inspection photo 1, 21 March 2024
  • Address The Bay construction site, Land Department inspection photo 2, 21 March 2024
  • Address The Bay construction site, Land Department inspection photo 3, 21 March 2024
  • Address The Bay construction site, Land Department inspection photo 4, 21 March 2024

9 October 2023

1.4%+1.4 pts

  • Address The Bay construction site, Land Department inspection photo 1, 9 October 2023
  • Address The Bay construction site, Land Department inspection photo 2, 9 October 2023
  • Address The Bay construction site, Land Department inspection photo 3, 9 October 2023
  • Address The Bay construction site, Land Department inspection photo 4, 9 October 2023

20 June 2023

0%+0.0 pts

  • Address The Bay construction site, Land Department inspection photo 1, 20 June 2023
  • Address The Bay construction site, Land Department inspection photo 2, 20 June 2023
  • Address The Bay construction site, Land Department inspection photo 3, 20 June 2023

All 61 site photos, by inspection date

Context

Dubai Harbour has 11 projects under construction, 35% built on average. Address The Bay is ahead of that average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Address The Bay?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Address The Bay be completed?
The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around June 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Address The Bay is built?
70%, measured at the Land Department site inspection on 15 July 2026. The Land Department engineers have inspected the site 11 times since March 2023.
Is Address The Bay delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Address The Bay?
The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
Which bank holds the escrow account for Address The Bay?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.