5242 construction photos

160 photos from 17 site inspections, newest first. The percentage is how much of 5242 was built on the day of each visit.

27 April 2021100% built

18 March 202197% built

19 January 202195% built

23 September 202093% built

15 June 202090% built

10 March 202086% built

11 November 201980% built

3 July 201967% built

26 February 201953% built

2 January 201946% built

24 October 201836% built

11 July 201830% built

21 March 201822% built

6 December 201715% built

26 July 201711% built

3 April 20176.9% built

19 December 20163.2% built

Back to 5242 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.