The St. Regis Residences, Downtown Dubai construction progress

The registered completion date for The St. Regis Residences, Downtown Dubai in DownTown Dubai is December 2026. At the last site inspection, in June 2026, it was 76% built. The developer is Emaar Development.

76%

Built, at the site inspection of 2 June 2026

On pace for its date

Registered completion date
December 2026
Finish at recent pace
January 2027
Construction started
February 2017
First registered
October 2016
Units
1,108
Escrow bank
Dubai Islamic Bank
Name in Arabic
ذا سانت ريجيز ريزيدنسز، داون تاون دبي
Project number
1816
Site inspections
14

Schedule

Since June 2025 The St. Regis Residences, Downtown Dubai has added about 3.1 points a month. That puts 100% around January 2027, within three months of its registered completion date of December 2026.

0%25%50%75%100%20182020202220242026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

2 June 2026

76%+10 pts

  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 1, 2 June 2026
  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 2, 2 June 2026
  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 3, 2 June 2026
  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 4, 2 June 2026

3 February 2026

66%+15 pts

  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 1, 3 February 2026
  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 2, 3 February 2026
  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 3, 3 February 2026
  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 4, 3 February 2026

1 October 2025

51%+10 pts

  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 1, 1 October 2025
  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 2, 1 October 2025
  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 3, 1 October 2025
  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 4, 1 October 2025

10 June 2025

40%+13 pts

  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 1, 10 June 2025
  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 2, 10 June 2025
  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 3, 10 June 2025
  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 4, 10 June 2025

29 January 2025

27%+6.7 pts

  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 1, 29 January 2025
  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 2, 29 January 2025
  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 3, 29 January 2025
  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 4, 29 January 2025

12 September 2024

20%+6.8 pts

  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 1, 12 September 2024
  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 2, 12 September 2024
  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 3, 12 September 2024
  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 4, 12 September 2024

6 May 2024

13%+4.1 pts

  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 1, 6 May 2024
  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 2, 6 May 2024
  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 3, 6 May 2024
  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 4, 6 May 2024

30 October 2023

9.2%+2.1 pts

  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 1, 30 October 2023
  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 2, 30 October 2023
  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 3, 30 October 2023
  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 4, 30 October 2023

4 July 2023

7.1%+1.6 pts

  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 1, 4 July 2023
  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 2, 4 July 2023
  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 3, 4 July 2023
  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 4, 4 July 2023

27 March 2023

5.5%+4.7 pts

  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 1, 27 March 2023
  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 2, 27 March 2023
  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 3, 27 March 2023
  • The St. Regis Residences, Downtown Dubai construction site, inspection photo 4, 27 March 2023

All 94 site photos, by inspection date

Context

DownTown Dubai has 13 projects under construction, 35% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The St. Regis Residences, Downtown Dubai?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The St. Regis Residences, Downtown Dubai handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The St. Regis Residences, Downtown Dubai?
The St. Regis Residences, Downtown Dubai was 76% built at the site inspection on 2 June 2026. The site has been inspected 14 times since December 2021. The Land Department took 94 site photos at its inspections.
Is The St. Regis Residences, Downtown Dubai delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of December 2026.
Who is building The St. Regis Residences, Downtown Dubai?
The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
Which bank holds the escrow account for The St. Regis Residences, Downtown Dubai?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.