Seapoint construction progress
Seapoint in Dubai Harbour is 37% built at the Land Department inspection of June 2026. Developer Emaar Development. Completion registered for March 2028.
37%
Built, at the Land Department site inspection of 24 June 2026
Running behind its date
- Completion date (Land Department)
- March 2028
- Finish at recent pace
- September 2028
- Construction started
- September 2023
- Registered with the Land Department
- April 2023
- Developer
- Emaar Development
- Community
- Dubai Harbour
- Units
- 674
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- سي بوينت
- Land Department project number
- 2633
- Land Department site inspections
- 9
Schedule
Between October 2025 and June 2026 the site added about 2.4 points a month. At that rate it would finish around September 2028, more than three months after the March 2028 date registered with the Land Department.
Site inspections
24 June 2026
37%+12 pts
4 February 2026
25%+9.2 pts
3 October 2025
16%+6.2 pts
23 May 2025
9.8%+3.2 pts
29 January 2025
6.6%+1.1 pts
10 October 2024
5.5%+5.1 pts
5 June 2024
0.4%+0.3 pts
8 November 2023
0.2%+0.2 pts
7 April 2023
0%
Context
Dubai Harbour has 11 projects under construction, 35% built on average.
Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Seapoint?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Seapoint be completed?
- The completion date registered with the Dubai Land Department is March 2028. At the pace of its recent inspections the site would reach 100% around September 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Seapoint is built?
- 37%, measured at the Land Department site inspection on 24 June 2026. The Land Department engineers have inspected the site 9 times since April 2023.
- Is Seapoint delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
- Who is building Seapoint?
- The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
- Which bank holds the escrow account for Seapoint?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The St. Regis Residences, Downtown DubaiAlso by Emaar Development. 76%, Due December 2026.
- Address The BayAlso by Emaar Development. 70%, Due December 2026.
- BayviewAlso by Emaar Development. 63%, Due July 2028.
- The Valley - RivanaAlso by Emaar Development. 94%, Due March 2027.
- Sobha Seahaven Tower ANearby in Dubai Harbour. 37%, Due April 2028.
- Damac BayNearby in Dubai Harbour. 34%, Due January 2027.
- Damac Bay 2Nearby in Dubai Harbour. 30%.
- Sobha Seahaven Tower B & CNearby in Dubai Harbour. 40%, Due October 2028.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

_page-0005.jpg&w=3840&q=75)
_4_11zon.jpg&w=3840&q=75)
.jpg&w=3840&q=75)














.jpg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)