Seapoint construction progress

The registered completion date for Seapoint in Dubai Harbour is March 2028. At the last site inspection, in June 2026, it was 37% built. The developer is Emaar Development.

37%

Built, at the site inspection of 24 June 2026

Running behind its date

Registered completion date
March 2028
Finish at recent pace
September 2028
Construction started
September 2023
First registered
April 2023
Community
Dubai Harbour
Units
674
Escrow bank
First Abu Dhabi Bank
Name in Arabic
سي بوينت
Project number
2633
Site inspections
9

Schedule

Between October 2025 and June 2026 the site added about 2.4 points a month. At that rate it would finish around September 2028, more than three months after its registered date of March 2028.

0%25%50%75%100%20242025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

24 June 2026

37%+12 pts

  • Seapoint construction site, inspection photo 1, 24 June 2026
  • Seapoint construction site, inspection photo 2, 24 June 2026
  • Seapoint construction site, inspection photo 3, 24 June 2026
  • Seapoint construction site, inspection photo 4, 24 June 2026

4 February 2026

25%+9.2 pts

  • Seapoint construction site, inspection photo 1, 4 February 2026
  • Seapoint construction site, inspection photo 2, 4 February 2026
  • Seapoint construction site, inspection photo 3, 4 February 2026
  • Seapoint construction site, inspection photo 4, 4 February 2026

3 October 2025

16%+6.2 pts

  • Seapoint construction site, inspection photo 1, 3 October 2025
  • Seapoint construction site, inspection photo 2, 3 October 2025
  • Seapoint construction site, inspection photo 3, 3 October 2025
  • Seapoint construction site, inspection photo 4, 3 October 2025

23 May 2025

9.8%+3.2 pts

  • Seapoint construction site, inspection photo 1, 23 May 2025
  • Seapoint construction site, inspection photo 2, 23 May 2025
  • Seapoint construction site, inspection photo 3, 23 May 2025
  • Seapoint construction site, inspection photo 4, 23 May 2025

29 January 2025

6.6%+1.1 pts

  • Seapoint construction site, inspection photo 1, 29 January 2025
  • Seapoint construction site, inspection photo 2, 29 January 2025
  • Seapoint construction site, inspection photo 3, 29 January 2025
  • Seapoint construction site, inspection photo 4, 29 January 2025

10 October 2024

5.5%+5.1 pts

  • Seapoint construction site, inspection photo 1, 10 October 2024
  • Seapoint construction site, inspection photo 2, 10 October 2024
  • Seapoint construction site, inspection photo 3, 10 October 2024
  • Seapoint construction site, inspection photo 4, 10 October 2024

5 June 2024

0.4%+0.3 pts

  • Seapoint construction site, inspection photo 1, 5 June 2024
  • Seapoint construction site, inspection photo 2, 5 June 2024

8 November 2023

0.2%+0.2 pts

  • Seapoint construction site, inspection photo 1, 8 November 2023
  • Seapoint construction site, inspection photo 2, 8 November 2023
  • Seapoint construction site, inspection photo 3, 8 November 2023

7 April 2023

0%

  • Seapoint construction site, inspection photo 1, 7 April 2023
  • Seapoint construction site, inspection photo 2, 7 April 2023
  • Seapoint construction site, inspection photo 3, 7 April 2023

All 57 site photos, by inspection date

Context

Dubai Harbour has 11 projects under construction, 36% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Seapoint?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Seapoint handover date?
The registered completion date is March 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Seapoint?
Seapoint was 37% built at the site inspection on 24 June 2026. The site has been inspected 9 times since April 2023. The Land Department took 57 site photos at its inspections.
Is Seapoint delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
Who is building Seapoint?
The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
Which bank holds the escrow account for Seapoint?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.