Bayview construction progress
The registered completion date for Bayview in Dubai Harbour is July 2028. At the last site inspection, in September 2026, it was 63% built. The developer is Emaar Development.
63%
Built, at the site inspection of 14 September 2026
On pace for its date
- Registered completion date
- July 2028
- Finish at recent pace
- July 2027
- Construction started
- October 2023
- First registered
- May 2023
- Developer
- Emaar Development
- Community
- Dubai Harbour
- Units
- 690
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- باي فيو
- Project number
- 2646
- Site inspections
- 10
Schedule
Since October 2025 Bayview has added about 3.6 points a month. That puts 100% around July 2027, within three months of its registered completion date of July 2028.
Site inspections
14 September 2026
63%+14 pts
30 June 2026
49%+14 pts
2 February 2026
35%+13 pts
3 October 2025
22%+4.1 pts
19 June 2025
18%+3.9 pts
9 March 2025
14%+5.1 pts
8 October 2024
9.1%+6.2 pts
26 April 2024
2.9%+2.8 pts
25 December 2023
0%+0.0 pts
8 May 2023
0%
Context
Dubai Harbour has 11 projects under construction, 36% built on average.
Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Bayview?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Bayview handover date?
- The registered completion date is July 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Bayview?
- Bayview was 63% built at the site inspection on 14 September 2026. The site has been inspected 10 times since May 2023. The Land Department took 61 site photos at its inspections.
- Is Bayview delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of July 2028.
- Who is building Bayview?
- The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
- Which bank holds the escrow account for Bayview?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The St. Regis Residences, Downtown DubaiAlso by Emaar Development. 76%, Due December 2026.
- Address The BayAlso by Emaar Development. 70%, Due December 2026.
- SeapointAlso by Emaar Development. 37%, Due March 2028.
- The Valley - RivanaAlso by Emaar Development. 95%, Due March 2027.
- Sobha Seahaven Tower ANearby in Dubai Harbour. 45%, Due April 2028.
- Damac BayNearby in Dubai Harbour. 34%, Due January 2027.
- Damac Bay 2Nearby in Dubai Harbour. 30%.
- Sobha Seahaven Tower B & CNearby in Dubai Harbour. 40%, Due October 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
_5_11zon.jpg&w=3840&q=75)
_5_11zon.jpg&w=3840&q=75)
_14_11zon.jpg&w=3840&q=75)


.jpg&w=3840&q=75)

.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


.jpg&w=3840&q=75)
.jpg&w=3840&q=75)











.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)