Millennium Binghatti Residences Business Bay construction progress

The register lists Millennium Binghatti Residences Business Bay in Business Bay as complete, with a registered completion date of July 2021. Its last site inspection on record was in July 2021. The developer is Binghatti Developers.

100%

Built, at the site inspection of 15 July 2021

Construction complete

Registered completion date
July 2021
Construction started
September 2017
First registered
February 2018
Community
Business Bay
Units
246
Escrow bank
Sharjah Islamic Bank
Name in Arabic
ميلينيوم بن غاطي ريزيدنسز الخليج التجاري
Project number
2014
Site inspections
6

Schedule

The register lists Millennium Binghatti Residences Business Bay as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2018201920202021
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

15 July 2021

100%+32 pts

  • Millennium Binghatti Residences Business Bay construction site, inspection photo 1, 15 July 2021
  • Millennium Binghatti Residences Business Bay construction site, inspection photo 2, 15 July 2021
  • Millennium Binghatti Residences Business Bay construction site, inspection photo 3, 15 July 2021
  • Millennium Binghatti Residences Business Bay construction site, inspection photo 4, 15 July 2021

17 November 2020

68%+24 pts

  • Millennium Binghatti Residences Business Bay construction site, inspection photo 1, 17 November 2020
  • Millennium Binghatti Residences Business Bay construction site, inspection photo 2, 17 November 2020
  • Millennium Binghatti Residences Business Bay construction site, inspection photo 3, 17 November 2020
  • Millennium Binghatti Residences Business Bay construction site, inspection photo 4, 17 November 2020

7 June 2020

44%+12 pts

  • Millennium Binghatti Residences Business Bay construction site, inspection photo 1, 7 June 2020
  • Millennium Binghatti Residences Business Bay construction site, inspection photo 2, 7 June 2020
  • Millennium Binghatti Residences Business Bay construction site, inspection photo 3, 7 June 2020
  • Millennium Binghatti Residences Business Bay construction site, inspection photo 4, 7 June 2020

21 January 2020

32%+8.8 pts

  • Millennium Binghatti Residences Business Bay construction site, inspection photo 1, 21 January 2020
  • Millennium Binghatti Residences Business Bay construction site, inspection photo 2, 21 January 2020
  • Millennium Binghatti Residences Business Bay construction site, inspection photo 3, 21 January 2020
  • Millennium Binghatti Residences Business Bay construction site, inspection photo 4, 21 January 2020

2 October 2019

24%+19 pts

  • Millennium Binghatti Residences Business Bay construction site, inspection photo 1, 2 October 2019
  • Millennium Binghatti Residences Business Bay construction site, inspection photo 2, 2 October 2019
  • Millennium Binghatti Residences Business Bay construction site, inspection photo 3, 2 October 2019
  • Millennium Binghatti Residences Business Bay construction site, inspection photo 4, 2 October 2019

6 February 2019

4.2%

  • Millennium Binghatti Residences Business Bay construction site, inspection photo 1, 6 February 2019
  • Millennium Binghatti Residences Business Bay construction site, inspection photo 2, 6 February 2019
  • Millennium Binghatti Residences Business Bay construction site, inspection photo 3, 6 February 2019
  • Millennium Binghatti Residences Business Bay construction site, inspection photo 4, 6 February 2019

All 55 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.

Own a unit in Millennium Binghatti Residences Business Bay?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Millennium Binghatti Residences Business Bay handover date?
Construction of Millennium Binghatti Residences Business Bay is recorded as complete, with a registered completion date of July 2021. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Millennium Binghatti Residences Business Bay?
Millennium Binghatti Residences Business Bay was 100% built at the site inspection on 15 July 2021. The site has been inspected 6 times since February 2019. The Land Department took 55 site photos at its inspections.
Is Millennium Binghatti Residences Business Bay delayed?
The register lists construction as complete.
Who is building Millennium Binghatti Residences Business Bay?
The registered developer is Binghatti Developers. It has 38 other projects under construction in Dubai.
Which bank holds the escrow account for Millennium Binghatti Residences Business Bay?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.