Burj Binghatti Jacob & Co. Residences construction photos

41 photos taken by Dubai Land Department engineers at 6 site inspections, newest first. The percentage is how much of Burj Binghatti Jacob & Co. Residences was built on the day of each visit.

31 August 202652% built

22 December 202535% built

28 July 202523% built

30 January 202513% built

31 August 20232.7% built

12 October 20220.1% built