Binghatti Canal construction progress

The register lists Binghatti Canal in Business Bay as complete, with a registered completion date of June 2023. Its last site inspection on record was in June 2023. The developer is Binghatti Developers.

100%

Built, at the site inspection of 21 June 2023

Construction complete

Registered completion date
June 2023
Construction started
January 2022
First registered
March 2022
Community
Business Bay
Units
306
Escrow bank
Sharjah Islamic Bank
Name in Arabic
بن غاطي كانال
Project number
2366
Site inspections
4

Schedule

The register lists Binghatti Canal as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2023
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

21 June 2023

100%+1.3 pts

  • Binghatti Canal construction site, inspection photo 1, 21 June 2023
  • Binghatti Canal construction site, inspection photo 2, 21 June 2023
  • Binghatti Canal construction site, inspection photo 3, 21 June 2023
  • Binghatti Canal construction site, inspection photo 4, 21 June 2023

22 May 2023

99%+43 pts

  • Binghatti Canal construction site, inspection photo 1, 22 May 2023
  • Binghatti Canal construction site, inspection photo 2, 22 May 2023
  • Binghatti Canal construction site, inspection photo 3, 22 May 2023
  • Binghatti Canal construction site, inspection photo 4, 22 May 2023

29 September 2022

56%+45 pts

  • Binghatti Canal construction site, inspection photo 1, 29 September 2022
  • Binghatti Canal construction site, inspection photo 2, 29 September 2022
  • Binghatti Canal construction site, inspection photo 3, 29 September 2022
  • Binghatti Canal construction site, inspection photo 4, 29 September 2022

21 April 2022

11%

  • Binghatti Canal construction site, inspection photo 1, 21 April 2022
  • Binghatti Canal construction site, inspection photo 2, 21 April 2022
  • Binghatti Canal construction site, inspection photo 3, 21 April 2022
  • Binghatti Canal construction site, inspection photo 4, 21 April 2022

All 40 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.

Own a unit in Binghatti Canal?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Binghatti Canal handover date?
Construction of Binghatti Canal is recorded as complete, with a registered completion date of June 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Binghatti Canal?
Binghatti Canal was 100% built at the site inspection on 21 June 2023. The site has been inspected 4 times since April 2022. The Land Department took 40 site photos at its inspections.
Is Binghatti Canal delayed?
The register lists construction as complete.
Who is building Binghatti Canal?
The registered developer is Binghatti Developers. It has 38 other projects under construction in Dubai.
Which bank holds the escrow account for Binghatti Canal?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.