Samana Green construction progress

The register lists Samana Green in Arjan as complete, with a registered completion date of December 2020. Its last site inspection on record was in February 2021. The developer is Samana International Real Estate Development.

100%

Built, at the site inspection of 11 February 2021

Construction complete

Registered completion date
December 2020
Construction started
February 2018
First registered
March 2018
Community
Arjan
Units
122
Escrow bank
Ajman Bank
Name in Arabic
سامانا كرين
Project number
2032
Site inspections
7

Schedule

The register lists Samana Green as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201920202021
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

11 February 2021

100%+17 pts

  • Samana Green construction site, inspection photo 1, 11 February 2021
  • Samana Green construction site, inspection photo 2, 11 February 2021
  • Samana Green construction site, inspection photo 3, 11 February 2021
  • Samana Green construction site, inspection photo 4, 11 February 2021

2 July 2020

83%+17 pts

  • Samana Green construction site, inspection photo 1, 2 July 2020
  • Samana Green construction site, inspection photo 2, 2 July 2020
  • Samana Green construction site, inspection photo 3, 2 July 2020
  • Samana Green construction site, inspection photo 4, 2 July 2020

10 March 2020

66%+8.4 pts

  • Samana Green construction site, inspection photo 1, 10 March 2020
  • Samana Green construction site, inspection photo 2, 10 March 2020
  • Samana Green construction site, inspection photo 3, 10 March 2020
  • Samana Green construction site, inspection photo 4, 10 March 2020

5 November 2019

57%+9.3 pts

  • Samana Green construction site, inspection photo 1, 5 November 2019
  • Samana Green construction site, inspection photo 2, 5 November 2019
  • Samana Green construction site, inspection photo 3, 5 November 2019
  • Samana Green construction site, inspection photo 4, 5 November 2019

10 July 2019

48%+16 pts

  • Samana Green construction site, inspection photo 1, 10 July 2019
  • Samana Green construction site, inspection photo 2, 10 July 2019
  • Samana Green construction site, inspection photo 3, 10 July 2019
  • Samana Green construction site, inspection photo 4, 10 July 2019

6 February 2019

32%+19 pts

  • Samana Green construction site, inspection photo 1, 6 February 2019
  • Samana Green construction site, inspection photo 2, 6 February 2019
  • Samana Green construction site, inspection photo 3, 6 February 2019
  • Samana Green construction site, inspection photo 4, 6 February 2019

12 September 2018

13%

  • Samana Green construction site, inspection photo 1, 12 September 2018
  • Samana Green construction site, inspection photo 2, 12 September 2018
  • Samana Green construction site, inspection photo 3, 12 September 2018
  • Samana Green construction site, inspection photo 4, 12 September 2018

All 66 site photos, by inspection date

Context

Arjan has 23 projects under construction, 48% built on average.

Samana International Real Estate Development has 14 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Samana Green?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Samana Green handover date?
Construction of Samana Green is recorded as complete, with a registered completion date of December 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Samana Green?
Samana Green was 100% built at the site inspection on 11 February 2021. The site has been inspected 7 times since September 2018. The Land Department took 66 site photos at its inspections.
Is Samana Green delayed?
The register lists construction as complete.
Who is building Samana Green?
The registered developer is Samana International Real Estate Development. It has 14 other projects under construction in Dubai.
Which bank holds the escrow account for Samana Green?
Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.