Samana Ivy Gardens construction progress

Samana Ivy Gardens in Dubai Land Residence Complex is 41% built at the Land Department inspection of April 2026. Developer Samana International Real Estate Development.

41%

Built, at the Land Department site inspection of 28 April 2026

Finish at recent pace
November 2029
Construction started
November 2023
Registered with the Land Department
June 2023
Units
374
Escrow bank
Emirates NBD
Name in Arabic
سمانا إيفي جارد نز
Land Department project number
2642
Land Department site inspections
6

Schedule

Since July 2025 Samana Ivy Gardens has added about 1.7 points a month. At that rate the site reaches 100% around November 2029. The Land Department has no completion date on record to compare it with.

0%25%50%75%100%202420252026
Progress at each Land Department site inspection

Site inspections

28 April 2026

27%+8.8 pts

  • Samana Ivy Gardens construction site, Land Department inspection photo 1, 28 April 2026
  • Samana Ivy Gardens construction site, Land Department inspection photo 2, 28 April 2026
  • Samana Ivy Gardens construction site, Land Department inspection photo 3, 28 April 2026
  • Samana Ivy Gardens construction site, Land Department inspection photo 4, 28 April 2026

27 December 2025

19%+6.3 pts

  • Samana Ivy Gardens construction site, Land Department inspection photo 1, 27 December 2025
  • Samana Ivy Gardens construction site, Land Department inspection photo 2, 27 December 2025
  • Samana Ivy Gardens construction site, Land Department inspection photo 3, 27 December 2025
  • Samana Ivy Gardens construction site, Land Department inspection photo 4, 27 December 2025

30 July 2025

12%+7.8 pts

  • Samana Ivy Gardens construction site, Land Department inspection photo 1, 30 July 2025
  • Samana Ivy Gardens construction site, Land Department inspection photo 2, 30 July 2025
  • Samana Ivy Gardens construction site, Land Department inspection photo 3, 30 July 2025
  • Samana Ivy Gardens construction site, Land Department inspection photo 4, 30 July 2025

7 February 2025

4.6%+4.0 pts

  • Samana Ivy Gardens construction site, Land Department inspection photo 1, 7 February 2025
  • Samana Ivy Gardens construction site, Land Department inspection photo 2, 7 February 2025
  • Samana Ivy Gardens construction site, Land Department inspection photo 3, 7 February 2025

14 May 2024

0.6%+0.6 pts

  • Samana Ivy Gardens construction site, Land Department inspection photo 1, 14 May 2024
  • Samana Ivy Gardens construction site, Land Department inspection photo 2, 14 May 2024
  • Samana Ivy Gardens construction site, Land Department inspection photo 3, 14 May 2024
  • Samana Ivy Gardens construction site, Land Department inspection photo 4, 14 May 2024

25 April 2023

0%

  • Samana Ivy Gardens construction site, Land Department inspection photo 1, 25 April 2023

All 25 site photos, by inspection date

Context

Dubai Land Residence Complex has 65 projects under construction, 24% built on average. Samana Ivy Gardens is ahead of that average.

Samana International Real Estate Development has 14 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Samana Ivy Gardens?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Samana Ivy Gardens be completed?
The Land Department has no completion date on record for Samana Ivy Gardens yet. It appears once the developer registers the construction timeline.
How much of Samana Ivy Gardens is built?
41%, measured at the Land Department site inspection on 28 April 2026. The Land Department engineers have inspected the site 6 times since April 2023.
Who is building Samana Ivy Gardens?
The registered developer is Samana International Real Estate Development. It has 13 other projects under construction in Dubai.
Which bank holds the escrow account for Samana Ivy Gardens?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.