Samana Ivy Gardens construction progress

No completion date is registered for Samana Ivy Gardens in Dubai Land Residence Complex yet. At the last site inspection, in October 2026, it was 41% built. The developer is Samana International Real Estate Development.

41%

Built, at the site inspection of 1 October 2026

Finish at recent pace
October 2028
Construction started
November 2023
First registered
June 2023
Units
374
Escrow bank
Emirates NBD
Name in Arabic
سمانا إيفي جارد نز
Project number
2642
Site inspections
7

Schedule

Since December 2025 Samana Ivy Gardens has added about 2.4 points a month. At that rate the site reaches 100% around October 2028. No completion date is on record to compare it with.

0%25%50%75%100%202420252026
Progress at each site inspection

Site inspections

1 October 2026

41%+13 pts

  • Samana Ivy Gardens construction site, inspection photo 1, 1 October 2026
  • Samana Ivy Gardens construction site, inspection photo 2, 1 October 2026
  • Samana Ivy Gardens construction site, inspection photo 3, 1 October 2026
  • Samana Ivy Gardens construction site, inspection photo 4, 1 October 2026

28 April 2026

27%+8.8 pts

  • Samana Ivy Gardens construction site, inspection photo 1, 28 April 2026
  • Samana Ivy Gardens construction site, inspection photo 2, 28 April 2026
  • Samana Ivy Gardens construction site, inspection photo 3, 28 April 2026
  • Samana Ivy Gardens construction site, inspection photo 4, 28 April 2026

27 December 2025

19%+6.3 pts

  • Samana Ivy Gardens construction site, inspection photo 1, 27 December 2025
  • Samana Ivy Gardens construction site, inspection photo 2, 27 December 2025
  • Samana Ivy Gardens construction site, inspection photo 3, 27 December 2025
  • Samana Ivy Gardens construction site, inspection photo 4, 27 December 2025

30 July 2025

12%+7.8 pts

  • Samana Ivy Gardens construction site, inspection photo 1, 30 July 2025
  • Samana Ivy Gardens construction site, inspection photo 2, 30 July 2025
  • Samana Ivy Gardens construction site, inspection photo 3, 30 July 2025
  • Samana Ivy Gardens construction site, inspection photo 4, 30 July 2025

7 February 2025

4.6%+4.0 pts

  • Samana Ivy Gardens construction site, inspection photo 1, 7 February 2025
  • Samana Ivy Gardens construction site, inspection photo 2, 7 February 2025
  • Samana Ivy Gardens construction site, inspection photo 3, 7 February 2025

14 May 2024

0.6%+0.6 pts

  • Samana Ivy Gardens construction site, inspection photo 1, 14 May 2024
  • Samana Ivy Gardens construction site, inspection photo 2, 14 May 2024
  • Samana Ivy Gardens construction site, inspection photo 3, 14 May 2024
  • Samana Ivy Gardens construction site, inspection photo 4, 14 May 2024

25 April 2023

0%

  • Samana Ivy Gardens construction site, inspection photo 1, 25 April 2023

All 33 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Samana International Real Estate Development has 14 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Samana Ivy Gardens?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Samana Ivy Gardens handover date?
No completion date is on record for Samana Ivy Gardens yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Samana Ivy Gardens?
Samana Ivy Gardens was 41% built at the site inspection on 1 October 2026. The site has been inspected 7 times since April 2023. The Land Department took 33 site photos at its inspections.
Who is building Samana Ivy Gardens?
The registered developer is Samana International Real Estate Development. It has 13 other projects under construction in Dubai.
Which bank holds the escrow account for Samana Ivy Gardens?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.