Samana Ivy Gardens construction progress
No completion date is registered for Samana Ivy Gardens in Dubai Land Residence Complex yet. At the last site inspection, in October 2026, it was 41% built. The developer is Samana International Real Estate Development.
41%
Built, at the site inspection of 1 October 2026
- Finish at recent pace
- October 2028
- Construction started
- November 2023
- First registered
- June 2023
- Community
- Dubai Land Residence Complex
- Units
- 374
- Escrow bank
- Emirates NBD
- Name in Arabic
- سمانا إيفي جارد نز
- Project number
- 2642
- Site inspections
- 7
Schedule
Since December 2025 Samana Ivy Gardens has added about 2.4 points a month. At that rate the site reaches 100% around October 2028. No completion date is on record to compare it with.
Site inspections
1 October 2026
41%+13 pts
28 April 2026
27%+8.8 pts
27 December 2025
19%+6.3 pts
30 July 2025
12%+7.8 pts
7 February 2025
4.6%+4.0 pts
14 May 2024
0.6%+0.6 pts
25 April 2023
0%
Context
Dubai Land Residence Complex has 63 projects under construction, 28% built on average.
Samana International Real Estate Development has 14 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Samana Ivy Gardens?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Samana Ivy Gardens handover date?
- No completion date is on record for Samana Ivy Gardens yet. Handover follows completion, so there is no date to give.
- What is the latest construction update on Samana Ivy Gardens?
- Samana Ivy Gardens was 41% built at the site inspection on 1 October 2026. The site has been inspected 7 times since April 2023. The Land Department took 33 site photos at its inspections.
- Who is building Samana Ivy Gardens?
- The registered developer is Samana International Real Estate Development. It has 13 other projects under construction in Dubai.
- Which bank holds the escrow account for Samana Ivy Gardens?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Samana MykonosAlso by Samana International Real Estate Development. 91%, Due April 2026, passed.
- Samana Mykonos SignatureAlso by Samana International Real Estate Development. 86%, Due April 2026, passed.
- Samana Golf ViewsAlso by Samana International Real Estate Development. 56%.
- Samana PortofinoAlso by Samana International Real Estate Development. 60%.
- Ag CentralNearby in Dubai Land Residence Complex. 59%, Due October 2026, passed.
- Ag SquareNearby in Dubai Land Residence Complex. 69%, Due September 2026, passed.
- Time 2Nearby in Dubai Land Residence Complex. 87%, Due June 2026, passed.
- Ag 7evenNearby in Dubai Land Residence Complex. 94%, Due March 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.