Samana Mykonos construction progress

Samana Mykonos in Dubai Studio City was registered to complete in April 2026 and is still under construction. At the last site inspection, in September 2026, it was 91% built. The developer is Samana International Real Estate Development.

91%

Built, at the site inspection of 29 September 2026

7 months past its registered completion date

Registered completion date
April 2026
Finish at recent pace
January 2027
Construction started
June 2023
First registered
February 2023
Units
198
Escrow bank
Emirates NBD
Name in Arabic
سامانا ميكونوس
Project number
2561
Site inspections
9

Schedule

Samana Mykonos was registered to complete in April 2026, 7 months ago, and is still under construction. Over the last year of inspections it has added about 2.6 points a month. Kept at that rate, the site would reach 100% around January 2027.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

29 September 2026

91%+10 pts

  • Samana Mykonos construction site, inspection photo 1, 29 September 2026
  • Samana Mykonos construction site, inspection photo 2, 29 September 2026
  • Samana Mykonos construction site, inspection photo 3, 29 September 2026
  • Samana Mykonos construction site, inspection photo 4, 29 September 2026

20 May 2026

81%+14 pts

  • Samana Mykonos construction site, inspection photo 1, 20 May 2026
  • Samana Mykonos construction site, inspection photo 2, 20 May 2026
  • Samana Mykonos construction site, inspection photo 3, 20 May 2026
  • Samana Mykonos construction site, inspection photo 4, 20 May 2026

4 February 2026

67%+1.7 pts

  • Samana Mykonos construction site, inspection photo 1, 4 February 2026
  • Samana Mykonos construction site, inspection photo 2, 4 February 2026
  • Samana Mykonos construction site, inspection photo 3, 4 February 2026
  • Samana Mykonos construction site, inspection photo 4, 4 February 2026

24 November 2025

65%+9.6 pts

  • Samana Mykonos construction site, inspection photo 1, 24 November 2025
  • Samana Mykonos construction site, inspection photo 2, 24 November 2025
  • Samana Mykonos construction site, inspection photo 3, 24 November 2025
  • Samana Mykonos construction site, inspection photo 4, 24 November 2025

16 July 2025

55%+17 pts

  • Samana Mykonos construction site, inspection photo 1, 16 July 2025
  • Samana Mykonos construction site, inspection photo 2, 16 July 2025
  • Samana Mykonos construction site, inspection photo 3, 16 July 2025
  • Samana Mykonos construction site, inspection photo 4, 16 July 2025

17 February 2025

38%+15 pts

  • Samana Mykonos construction site, inspection photo 1, 17 February 2025
  • Samana Mykonos construction site, inspection photo 2, 17 February 2025
  • Samana Mykonos construction site, inspection photo 3, 17 February 2025
  • Samana Mykonos construction site, inspection photo 4, 17 February 2025

31 October 2024

23%+12 pts

  • Samana Mykonos construction site, inspection photo 1, 31 October 2024
  • Samana Mykonos construction site, inspection photo 2, 31 October 2024
  • Samana Mykonos construction site, inspection photo 3, 31 October 2024
  • Samana Mykonos construction site, inspection photo 4, 31 October 2024

7 May 2024

11%+11 pts

  • Samana Mykonos construction site, inspection photo 1, 7 May 2024
  • Samana Mykonos construction site, inspection photo 2, 7 May 2024
  • Samana Mykonos construction site, inspection photo 3, 7 May 2024
  • Samana Mykonos construction site, inspection photo 4, 7 May 2024

20 January 2023

0%

  • Samana Mykonos construction site, inspection photo 1, 20 January 2023
  • Samana Mykonos construction site, inspection photo 2, 20 January 2023
  • Samana Mykonos construction site, inspection photo 3, 20 January 2023
  • Samana Mykonos construction site, inspection photo 4, 20 January 2023

All 66 site photos, by inspection date

Context

Dubai Studio City has 8 projects under construction, 53% built on average.

Samana International Real Estate Development has 14 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Samana Mykonos?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Samana Mykonos handover date?
The registered completion date was April 2026, and the register still lists Samana Mykonos as under construction. At the pace of its recent inspections the site would reach 100% around January 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Samana Mykonos?
Samana Mykonos was 91% built at the site inspection on 29 September 2026. The site has been inspected 9 times since January 2023. The Land Department took 66 site photos at its inspections.
Is Samana Mykonos delayed?
Yes. Its registered completion date of April 2026 has passed and the project is still listed as under construction.
Who is building Samana Mykonos?
The registered developer is Samana International Real Estate Development. It has 13 other projects under construction in Dubai.
Which bank holds the escrow account for Samana Mykonos?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.