Samana Mykonos construction progress
Samana Mykonos in Dubai Studio City is 91% built at the Land Department inspection of September 2026. Developer Samana International Real Estate Development. Completion registered for April 2026.
91%
Built, at the Land Department site inspection of 29 September 2026
5 months past its registered completion date
- Completion date (Land Department)
- April 2026
- Finish at recent pace
- January 2027
- Construction started
- June 2023
- Registered with the Land Department
- February 2023
- Community
- Dubai Studio City
- Units
- 198
- Escrow bank
- Emirates NBD
- Name in Arabic
- سامانا ميكونوس
- Land Department project number
- 2561
- Land Department site inspections
- 9
Schedule
Samana Mykonos was registered to complete in April 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 2.6 points a month. Kept at that rate, the site would reach 100% around January 2027.
Site inspections
29 September 2026
91%+10 pts
20 May 2026
81%+14 pts
4 February 2026
67%+1.7 pts
24 November 2025
65%+9.6 pts
16 July 2025
55%+17 pts
17 February 2025
38%+15 pts
31 October 2024
23%+12 pts
7 May 2024
11%+11 pts
20 January 2023
0%
Context
Dubai Studio City has 8 projects under construction, 51% built on average.
Samana International Real Estate Development has 14 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Samana Mykonos?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Samana Mykonos be completed?
- The completion date registered with the Dubai Land Department is April 2026. At the pace of its recent inspections the site would reach 100% around January 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Samana Mykonos is built?
- 91%, measured at the Land Department site inspection on 29 September 2026. The Land Department engineers have inspected the site 9 times since January 2023.
- Is Samana Mykonos delayed?
- Yes. Its registered completion date of April 2026 has passed and the Land Department still lists it as under construction.
- Who is building Samana Mykonos?
- The registered developer is Samana International Real Estate Development. It has 13 other projects under construction in Dubai.
- Which bank holds the escrow account for Samana Mykonos?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Samana Mykonos SignatureAlso by Samana International Real Estate Development. 80%, Due April 2026, passed.
- Samana Ivy GardensAlso by Samana International Real Estate Development. 41%.
- Samana Golf ViewsAlso by Samana International Real Estate Development. 56%.
- Samana PortofinoAlso by Samana International Real Estate Development. 60%.
- Laya CourtyardNearby in Dubai Studio City. 51%, Due December 2026.
- Beach Oasis 2Nearby in Dubai Studio City. 53%, Due April 2026, passed.
- Arisha TerracesNearby in Dubai Studio City. 34%, Due October 2027.
- Ghaff Land ResidenceNearby in Dubai Studio City. 64%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.