Samana Mykonos construction progress

Samana Mykonos in Dubai Studio City is 91% built at the Land Department inspection of September 2026. Developer Samana International Real Estate Development. Completion registered for April 2026.

91%

Built, at the Land Department site inspection of 29 September 2026

5 months past its registered completion date

Completion date (Land Department)
April 2026
Finish at recent pace
January 2027
Construction started
June 2023
Registered with the Land Department
February 2023
Units
198
Escrow bank
Emirates NBD
Name in Arabic
سامانا ميكونوس
Land Department project number
2561
Land Department site inspections
9

Schedule

Samana Mykonos was registered to complete in April 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 2.6 points a month. Kept at that rate, the site would reach 100% around January 2027.

0%25%50%75%100%202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

29 September 2026

91%+10 pts

  • Samana Mykonos construction site, Land Department inspection photo 1, 29 September 2026
  • Samana Mykonos construction site, Land Department inspection photo 2, 29 September 2026
  • Samana Mykonos construction site, Land Department inspection photo 3, 29 September 2026
  • Samana Mykonos construction site, Land Department inspection photo 4, 29 September 2026

20 May 2026

81%+14 pts

  • Samana Mykonos construction site, Land Department inspection photo 1, 20 May 2026
  • Samana Mykonos construction site, Land Department inspection photo 2, 20 May 2026
  • Samana Mykonos construction site, Land Department inspection photo 3, 20 May 2026
  • Samana Mykonos construction site, Land Department inspection photo 4, 20 May 2026

4 February 2026

67%+1.7 pts

  • Samana Mykonos construction site, Land Department inspection photo 1, 4 February 2026
  • Samana Mykonos construction site, Land Department inspection photo 2, 4 February 2026
  • Samana Mykonos construction site, Land Department inspection photo 3, 4 February 2026
  • Samana Mykonos construction site, Land Department inspection photo 4, 4 February 2026

24 November 2025

65%+9.6 pts

  • Samana Mykonos construction site, Land Department inspection photo 1, 24 November 2025
  • Samana Mykonos construction site, Land Department inspection photo 2, 24 November 2025
  • Samana Mykonos construction site, Land Department inspection photo 3, 24 November 2025
  • Samana Mykonos construction site, Land Department inspection photo 4, 24 November 2025

16 July 2025

55%+17 pts

  • Samana Mykonos construction site, Land Department inspection photo 1, 16 July 2025
  • Samana Mykonos construction site, Land Department inspection photo 2, 16 July 2025
  • Samana Mykonos construction site, Land Department inspection photo 3, 16 July 2025
  • Samana Mykonos construction site, Land Department inspection photo 4, 16 July 2025

17 February 2025

38%+15 pts

  • Samana Mykonos construction site, Land Department inspection photo 1, 17 February 2025
  • Samana Mykonos construction site, Land Department inspection photo 2, 17 February 2025
  • Samana Mykonos construction site, Land Department inspection photo 3, 17 February 2025
  • Samana Mykonos construction site, Land Department inspection photo 4, 17 February 2025

31 October 2024

23%+12 pts

  • Samana Mykonos construction site, Land Department inspection photo 1, 31 October 2024
  • Samana Mykonos construction site, Land Department inspection photo 2, 31 October 2024
  • Samana Mykonos construction site, Land Department inspection photo 3, 31 October 2024
  • Samana Mykonos construction site, Land Department inspection photo 4, 31 October 2024

7 May 2024

11%+11 pts

  • Samana Mykonos construction site, Land Department inspection photo 1, 7 May 2024
  • Samana Mykonos construction site, Land Department inspection photo 2, 7 May 2024
  • Samana Mykonos construction site, Land Department inspection photo 3, 7 May 2024
  • Samana Mykonos construction site, Land Department inspection photo 4, 7 May 2024

20 January 2023

0%

  • Samana Mykonos construction site, Land Department inspection photo 1, 20 January 2023
  • Samana Mykonos construction site, Land Department inspection photo 2, 20 January 2023
  • Samana Mykonos construction site, Land Department inspection photo 3, 20 January 2023
  • Samana Mykonos construction site, Land Department inspection photo 4, 20 January 2023

All 66 site photos, by inspection date

Context

Dubai Studio City has 8 projects under construction, 51% built on average.

Samana International Real Estate Development has 14 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Samana Mykonos?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Samana Mykonos be completed?
The completion date registered with the Dubai Land Department is April 2026. At the pace of its recent inspections the site would reach 100% around January 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Samana Mykonos is built?
91%, measured at the Land Department site inspection on 29 September 2026. The Land Department engineers have inspected the site 9 times since January 2023.
Is Samana Mykonos delayed?
Yes. Its registered completion date of April 2026 has passed and the Land Department still lists it as under construction.
Who is building Samana Mykonos?
The registered developer is Samana International Real Estate Development. It has 13 other projects under construction in Dubai.
Which bank holds the escrow account for Samana Mykonos?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.