Samana Green construction photos
66 photos from 7 site inspections, newest first. The percentage is how much of Samana Green was built on the day of each visit.
11 February 2021100% built
2 July 202083% built
10 March 202066% built
5 November 201957% built
10 July 201948% built
6 February 201932% built
12 September 201813% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.