Skip to content

Talia Residences construction progress

The register lists Talia Residences in Al Furjan as complete, with a registered completion date of April 2025. Its last site inspection on record was in May 2026. The developer is Deyaar Development.

100%

Built, at the site inspection of 22 May 2026

Construction complete

Registered completion date
April 2025
Construction started
March 2023
First registered
March 2023
Community
Al Furjan
Units
160
Escrow bank
Dubai Islamic Bank
Name in Arabic
تاليا ريزيدنسز
Project number
2570
Site inspections
8

Schedule

The register lists Talia Residences as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

22 May 2026

100%+2.6 pts

  • Talia Residences construction site, inspection photo 1, 22 May 2026
  • Talia Residences construction site, inspection photo 2, 22 May 2026
  • Talia Residences construction site, inspection photo 3, 22 May 2026
  • Talia Residences construction site, inspection photo 4, 22 May 2026

29 April 2026

97%+1.7 pts

  • Talia Residences construction site, inspection photo 1, 29 April 2026
  • Talia Residences construction site, inspection photo 2, 29 April 2026
  • Talia Residences construction site, inspection photo 3, 29 April 2026
  • Talia Residences construction site, inspection photo 4, 29 April 2026

17 March 2026

96%+3.7 pts

  • Talia Residences construction site, inspection photo 1, 17 March 2026
  • Talia Residences construction site, inspection photo 2, 17 March 2026
  • Talia Residences construction site, inspection photo 3, 17 March 2026
  • Talia Residences construction site, inspection photo 4, 17 March 2026

27 November 2025

92%+31 pts

  • Talia Residences construction site, inspection photo 1, 27 November 2025
  • Talia Residences construction site, inspection photo 2, 27 November 2025
  • Talia Residences construction site, inspection photo 3, 27 November 2025
  • Talia Residences construction site, inspection photo 4, 27 November 2025

3 March 2025

61%+32 pts

  • Talia Residences construction site, inspection photo 1, 3 March 2025
  • Talia Residences construction site, inspection photo 2, 3 March 2025
  • Talia Residences construction site, inspection photo 3, 3 March 2025
  • Talia Residences construction site, inspection photo 4, 3 March 2025

22 July 2024

30%+18 pts

  • Talia Residences construction site, inspection photo 1, 22 July 2024
  • Talia Residences construction site, inspection photo 2, 22 July 2024
  • Talia Residences construction site, inspection photo 3, 22 July 2024
  • Talia Residences construction site, inspection photo 4, 22 July 2024

14 March 2024

12%+12 pts

  • Talia Residences construction site, inspection photo 1, 14 March 2024
  • Talia Residences construction site, inspection photo 2, 14 March 2024
  • Talia Residences construction site, inspection photo 3, 14 March 2024
  • Talia Residences construction site, inspection photo 4, 14 March 2024

6 February 2023

0%

  • Talia Residences construction site, inspection photo 1, 6 February 2023
  • Talia Residences construction site, inspection photo 2, 6 February 2023
  • Talia Residences construction site, inspection photo 3, 6 February 2023

All 64 site photos, by inspection date

Context

Al Furjan has 38 projects under construction, 32% built on average.

Deyaar Development has 9 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Talia Residences?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Talia Residences handover date?
Construction of Talia Residences is recorded as complete, with a registered completion date of April 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Talia Residences?
Talia Residences was 100% built at the site inspection on 22 May 2026. The site has been inspected 8 times since February 2023. The Land Department took 64 site photos at its inspections.
Is Talia Residences delayed?
The register lists construction as complete.
Who is building Talia Residences?
The registered developer is Deyaar Development. It has 9 other projects under construction in Dubai.
Which bank holds the escrow account for Talia Residences?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.