Skip to content

Ember At Park Five construction progress

The registered completion date for Ember At Park Five in International Media Production Zone is June 2027. At the last site inspection, in September 2026, it was 18% built. The developer is Deyaar Development.

18%

Built, at the site inspection of 17 September 2026

Running behind its date

Registered completion date
June 2027
Finish at recent pace
June 2030
Construction started
April 2025
First registered
December 2024
Units
205
Escrow bank
Dubai Islamic Bank
Name in Arabic
إيمبر في بارك فايف
Project number
3344
Site inspections
3

Schedule

Between June 2026 and September 2026 the site added about 1.8 points a month. At that rate it would finish around June 2030, more than three months after its registered date of June 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 September 2026

18%+4.8 pts

  • Ember At Park Five construction site, inspection photo 1, 17 September 2026
  • Ember At Park Five construction site, inspection photo 2, 17 September 2026
  • Ember At Park Five construction site, inspection photo 3, 17 September 2026
  • Ember At Park Five construction site, inspection photo 4, 17 September 2026

29 June 2026

13%+13 pts

  • Ember At Park Five construction site, inspection photo 1, 29 June 2026
  • Ember At Park Five construction site, inspection photo 2, 29 June 2026
  • Ember At Park Five construction site, inspection photo 3, 29 June 2026
  • Ember At Park Five construction site, inspection photo 4, 29 June 2026

23 October 2024

0%

  • Ember At Park Five construction site, inspection photo 1, 23 October 2024
  • Ember At Park Five construction site, inspection photo 2, 23 October 2024

All 14 site photos, by inspection date

Context

International Media Production Zone has 15 projects under construction, 23% built on average.

Deyaar Development has 9 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Ember At Park Five?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Ember At Park Five handover date?
The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Ember At Park Five?
Ember At Park Five was 18% built at the site inspection on 17 September 2026. The site has been inspected 3 times since October 2024. The Land Department took 14 site photos at its inspections.
Is Ember At Park Five delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
Who is building Ember At Park Five?
The registered developer is Deyaar Development. It has 8 other projects under construction in Dubai.
Which bank holds the escrow account for Ember At Park Five?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.