Montrell Hotel Aprtments construction progress

The register lists Montrell Hotel Aprtments in Al Furjan as complete, with a registered completion date of March 2018. Its last site inspection on record was in September 2019. The developer is Azizi Developments.

100%

Built, at the site inspection of 10 September 2019

Construction complete

Registered completion date
March 2018
Construction started
May 2016
First registered
June 2016
Community
Al Furjan
Units
224
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
مونتريل للشقق الفندقية
Project number
1763
Site inspections
6

Schedule

The register lists Montrell Hotel Aprtments as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201720182019
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

10 September 2019

100%+1.6 pts

  • Montrell Hotel Aprtments construction site, inspection photo 1, 10 September 2019
  • Montrell Hotel Aprtments construction site, inspection photo 2, 10 September 2019
  • Montrell Hotel Aprtments construction site, inspection photo 3, 10 September 2019
  • Montrell Hotel Aprtments construction site, inspection photo 4, 10 September 2019

11 March 2018

98%+7.3 pts

  • Montrell Hotel Aprtments construction site, inspection photo 1, 11 March 2018
  • Montrell Hotel Aprtments construction site, inspection photo 2, 11 March 2018
  • Montrell Hotel Aprtments construction site, inspection photo 3, 11 March 2018
  • Montrell Hotel Aprtments construction site, inspection photo 4, 11 March 2018

26 December 2017

91%+19 pts

  • Montrell Hotel Aprtments construction site, inspection photo 1, 26 December 2017
  • Montrell Hotel Aprtments construction site, inspection photo 2, 26 December 2017
  • Montrell Hotel Aprtments construction site, inspection photo 3, 26 December 2017
  • Montrell Hotel Aprtments construction site, inspection photo 4, 26 December 2017

28 August 2017

72%+28 pts

  • Montrell Hotel Aprtments construction site, inspection photo 1, 28 August 2017
  • Montrell Hotel Aprtments construction site, inspection photo 2, 28 August 2017
  • Montrell Hotel Aprtments construction site, inspection photo 3, 28 August 2017
  • Montrell Hotel Aprtments construction site, inspection photo 4, 28 August 2017

25 April 2017

44%+24 pts

  • Montrell Hotel Aprtments construction site, inspection photo 1, 25 April 2017
  • Montrell Hotel Aprtments construction site, inspection photo 2, 25 April 2017
  • Montrell Hotel Aprtments construction site, inspection photo 3, 25 April 2017
  • Montrell Hotel Aprtments construction site, inspection photo 4, 25 April 2017

19 December 2016

20%

  • Montrell Hotel Aprtments construction site, inspection photo 1, 19 December 2016
  • Montrell Hotel Aprtments construction site, inspection photo 2, 19 December 2016
  • Montrell Hotel Aprtments construction site, inspection photo 3, 19 December 2016
  • Montrell Hotel Aprtments construction site, inspection photo 4, 19 December 2016

All 64 site photos, by inspection date

Context

Al Furjan has 38 projects under construction, 32% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Montrell Hotel Aprtments?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Montrell Hotel Aprtments handover date?
Construction of Montrell Hotel Aprtments is recorded as complete, with a registered completion date of March 2018. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Montrell Hotel Aprtments?
Montrell Hotel Aprtments was 100% built at the site inspection on 10 September 2019. The site has been inspected 6 times since December 2016. The Land Department took 64 site photos at its inspections.
Is Montrell Hotel Aprtments delayed?
The register lists construction as complete.
Who is building Montrell Hotel Aprtments?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Montrell Hotel Aprtments?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.