Montrell Hotel Aprtments construction photos

64 photos from 6 site inspections, newest first. The percentage is how much of Montrell Hotel Aprtments was built on the day of each visit.

10 September 2019100% built

11 March 201898% built

26 December 201791% built

28 August 201772% built

25 April 201744% built

19 December 201620% built

Back to Montrell Hotel Aprtments construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.