Binghatti Stars construction progress

The register lists Binghatti Stars in Silicon Oasis as complete, with a registered completion date of January 2020. Its last site inspection on record was in January 2020. The developer is Binghatti Developers.

100%

Built, at the site inspection of 28 January 2020

Construction complete

Registered completion date
January 2020
Construction started
June 2017
First registered
September 2017
Community
Silicon Oasis
Units
362
Escrow bank
Sharjah Islamic Bank
Name in Arabic
بن غاطي ستارز
Project number
1933
Site inspections
5

Schedule

The register lists Binghatti Stars as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201820192020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

28 January 2020

100%+9.8 pts

  • Binghatti Stars construction site, inspection photo 1, 28 January 2020
  • Binghatti Stars construction site, inspection photo 2, 28 January 2020
  • Binghatti Stars construction site, inspection photo 3, 28 January 2020
  • Binghatti Stars construction site, inspection photo 4, 28 January 2020

4 September 2019

90%+40 pts

  • Binghatti Stars construction site, inspection photo 1, 4 September 2019
  • Binghatti Stars construction site, inspection photo 2, 4 September 2019
  • Binghatti Stars construction site, inspection photo 3, 4 September 2019
  • Binghatti Stars construction site, inspection photo 4, 4 September 2019

20 November 2018

50%+17 pts

  • Binghatti Stars construction site, inspection photo 1, 20 November 2018
  • Binghatti Stars construction site, inspection photo 2, 20 November 2018
  • Binghatti Stars construction site, inspection photo 3, 20 November 2018
  • Binghatti Stars construction site, inspection photo 4, 20 November 2018

2 September 2018

33%+13 pts

  • Binghatti Stars construction site, inspection photo 1, 2 September 2018
  • Binghatti Stars construction site, inspection photo 2, 2 September 2018
  • Binghatti Stars construction site, inspection photo 3, 2 September 2018
  • Binghatti Stars construction site, inspection photo 4, 2 September 2018

26 March 2018

20%

  • Binghatti Stars construction site, inspection photo 1, 26 March 2018
  • Binghatti Stars construction site, inspection photo 2, 26 March 2018
  • Binghatti Stars construction site, inspection photo 3, 26 March 2018
  • Binghatti Stars construction site, inspection photo 4, 26 March 2018

All 57 site photos, by inspection date

Context

Silicon Oasis has 10 projects under construction, 28% built on average.

Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.

Own a unit in Binghatti Stars?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Binghatti Stars handover date?
Construction of Binghatti Stars is recorded as complete, with a registered completion date of January 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Binghatti Stars?
Binghatti Stars was 100% built at the site inspection on 28 January 2020. The site has been inspected 5 times since March 2018. The Land Department took 57 site photos at its inspections.
Is Binghatti Stars delayed?
The register lists construction as complete.
Who is building Binghatti Stars?
The registered developer is Binghatti Developers. It has 38 other projects under construction in Dubai.
Which bank holds the escrow account for Binghatti Stars?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.