Oasiz 2 By Danube construction progress

The registered completion date for Oasiz 2 By Danube in Silicon Oasis is November 2027. At the last site inspection, in November 2026, it was 38% built. The developer is Danube Properties Development.

38%

Built, at the site inspection of 17 November 2026

Running behind its date

Registered completion date
November 2027
Finish at recent pace
January 2029
Construction started
December 2024
First registered
October 2024
Community
Silicon Oasis
Units
483
Escrow bank
Ajman Bank
Name in Arabic
أويسز 2 من دانوب
Project number
3260
Site inspections
7

Schedule

Between December 2025 and November 2026 the site added about 2.4 points a month. At that rate it would finish around January 2029, more than three months after its registered date of November 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 November 2026

38%+6.9 pts

  • Oasiz 2 By Danube construction site, inspection photo 1, 17 November 2026
  • Oasiz 2 By Danube construction site, inspection photo 2, 17 November 2026
  • Oasiz 2 By Danube construction site, inspection photo 3, 17 November 2026
  • Oasiz 2 By Danube construction site, inspection photo 4, 17 November 2026

29 July 2026

31%+12 pts

  • Oasiz 2 By Danube construction site, inspection photo 1, 29 July 2026
  • Oasiz 2 By Danube construction site, inspection photo 2, 29 July 2026
  • Oasiz 2 By Danube construction site, inspection photo 3, 29 July 2026
  • Oasiz 2 By Danube construction site, inspection photo 4, 29 July 2026

15 April 2026

19%+6.5 pts

  • Oasiz 2 By Danube construction site, inspection photo 1, 15 April 2026
  • Oasiz 2 By Danube construction site, inspection photo 2, 15 April 2026
  • Oasiz 2 By Danube construction site, inspection photo 3, 15 April 2026
  • Oasiz 2 By Danube construction site, inspection photo 4, 15 April 2026

24 December 2025

12%+6.7 pts

  • Oasiz 2 By Danube construction site, inspection photo 1, 24 December 2025
  • Oasiz 2 By Danube construction site, inspection photo 2, 24 December 2025
  • Oasiz 2 By Danube construction site, inspection photo 3, 24 December 2025
  • Oasiz 2 By Danube construction site, inspection photo 4, 24 December 2025

16 September 2025

5.3%+3.5 pts

  • Oasiz 2 By Danube construction site, inspection photo 1, 16 September 2025
  • Oasiz 2 By Danube construction site, inspection photo 2, 16 September 2025
  • Oasiz 2 By Danube construction site, inspection photo 3, 16 September 2025
  • Oasiz 2 By Danube construction site, inspection photo 4, 16 September 2025

3 June 2025

1.8%+1.8 pts

  • Oasiz 2 By Danube construction site, inspection photo 1, 3 June 2025
  • Oasiz 2 By Danube construction site, inspection photo 2, 3 June 2025
  • Oasiz 2 By Danube construction site, inspection photo 3, 3 June 2025
  • Oasiz 2 By Danube construction site, inspection photo 4, 3 June 2025

3 September 2024

0%

  • Oasiz 2 By Danube construction site, inspection photo 1, 3 September 2024
  • Oasiz 2 By Danube construction site, inspection photo 2, 3 September 2024

All 40 site photos, by inspection date

Context

Silicon Oasis has 10 projects under construction, 28% built on average.

Danube Properties Development has 23 projects under construction in Dubai; 4 have passed their registered completion date.

Own a unit in Oasiz 2 By Danube?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Oasiz 2 By Danube handover date?
The registered completion date is November 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Oasiz 2 By Danube?
Oasiz 2 By Danube was 38% built at the site inspection on 17 November 2026. The site has been inspected 7 times since September 2024. The Land Department took 40 site photos at its inspections.
Is Oasiz 2 By Danube delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
Who is building Oasiz 2 By Danube?
The registered developer is Danube Properties Development. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Oasiz 2 By Danube?
Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.