Oasiz 1 By Danube construction progress
Oasiz 1 By Danube in Silicon Oasis is 30% built at the Land Department inspection of July 2026. Developer Danube Properties Development. Completion registered for November 2027.
30%
Built, at the Land Department site inspection of 29 July 2026
Running behind its date
- Completion date (Land Department)
- November 2027
- Finish at recent pace
- June 2029
- Construction started
- December 2024
- Registered with the Land Department
- September 2024
- Developer
- Danube Properties Development
- Community
- Silicon Oasis
- Units
- 410
- Escrow bank
- Ajman Bank
- Name in Arabic
- أويسز 1 من دانوب
- Land Department project number
- 3259
- Land Department site inspections
- 6
Schedule
Between September 2025 and July 2026 the site added about 2.0 points a month. At that rate it would finish around June 2029, more than three months after the November 2027 date registered with the Land Department.
Site inspections
29 July 2026
30%+10 pts
15 April 2026
20%+6.5 pts
24 December 2025
14%+4.3 pts
16 September 2025
9.5%+3.8 pts
3 June 2025
5.7%+5.7 pts
3 September 2024
0%
Context
Silicon Oasis has 11 projects under construction, 32% built on average.
Danube Properties Development has 23 projects under construction in Dubai; 4 have passed their registered completion date.
Own a unit in Oasiz 1 By Danube?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Oasiz 1 By Danube be completed?
- The completion date registered with the Dubai Land Department is November 2027. At the pace of its recent inspections the site would reach 100% around June 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Oasiz 1 By Danube is built?
- 30%, measured at the Land Department site inspection on 29 July 2026. The Land Department engineers have inspected the site 6 times since September 2024.
- Is Oasiz 1 By Danube delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
- Who is building Oasiz 1 By Danube?
- The registered developer is Danube Properties Development. It has 22 other projects under construction in Dubai.
- Which bank holds the escrow account for Oasiz 1 By Danube?
- Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Elitz By DanubeAlso by Danube Properties Development. 81%, Due December 2025, passed.
- Viewz 1 By DanubeAlso by Danube Properties Development. 50%, Due June 2026, passed.
- Viewz 2 By DanubeAlso by Danube Properties Development. 50%, Due June 2026, passed.
- Fashionz 1 By DanubeAlso by Danube Properties Development. 40%.
- Tria By DeyaarNearby in Silicon Oasis. 94%, Due June 2025, passed.
- SerenovaNearby in Silicon Oasis. 1.6%, Due March 2028.
- Aura EliteNearby in Silicon Oasis. 44%, Due April 2026, passed.
- Oasis LoftNearby in Silicon Oasis. 50%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)


.jpg&w=3840&q=75)