Off-plan projects in Silicon Oasis
10 projects in Silicon Oasis are under construction. On average they are 28% built. 3 have passed their registered completion date. The next one due is Solen Residence By Jamal Living, in October 2027.
- Aura EliteAura Infinite Real Estate Development51%Due April 2026, passed
- Oasis LoftOasis Lofts Properties50%Due September 2026, passed
- Aura PrestigeAura Infinite Real Estate Development40%Due November 2026, passed
- Oasiz 1 By DanubeDanube Properties Development38%Due November 2027
- Oasiz 2 By DanubeDanube Properties Development38%Due November 2027
- Solen Residence By Jamal LivingMohammad Abuhijleh Real Estate Development22%Due October 2027
- Timez By DanubeDanube Properties Development21%Due July 2028
- Belle Vie By ZimayaZimaya Properties11%Due March 2028
- The HillgateEllington Properties Development3.1%Due June 2028
- SerenovaPob1 Properties1.6%Due March 2028
Questions
How many off-plan projects are under construction in Silicon Oasis?
10 projects are under construction in Silicon Oasis, 28% built on average at the latest site inspections.
Which Silicon Oasis projects are due to finish next?
By registered completion date: Solen Residence By Jamal Living (October 2027, 22% built), Oasiz 1 By Danube (November 2027, 38% built) and Oasiz 2 By Danube (November 2027, 38% built). RERA asks developers to update these dates as projects move, so check the register before relying on one.
How many Silicon Oasis projects are past their completion date?
3 of 10, among them Aura Elite, Oasis Loft and Aura Prestige. A project counts as late once its registered completion date has passed before it reaches 100%.
Which developers are building in Silicon Oasis?
The developers with the most projects here are Danube Properties Development (3) and Aura Infinite Real Estate Development (2), out of 7 building in Silicon Oasis.
Reading these figures
Each percentage is the share of construction recorded at the latest site inspection. The completion date is the one the developer registered, and RERA asks developers to update it when it reviews a project. Open a project to see its latest inspections, the site photos and whether it is keeping pace with that date.
What happens at handover and how to snag a new home cover the steps after 100%.
Source: the Dubai Land Department’s Mashrooi register, read daily. Projects listed as cancelled or finished are not shown.