Aura Elite construction progress
Aura Elite in Silicon Oasis is 44% built at the Land Department inspection of September 2026. Developer Aura Infinite Real Estate Development. Completion registered for April 2026.
44%
Built, at the Land Department site inspection of 24 September 2026
5 months past its registered completion date
- Completion date (Land Department)
- April 2026
- Finish at recent pace
- April 2028
- Construction started
- September 2024
- Registered with the Land Department
- January 2025
- Developer
- Aura Infinite Real Estate Development
- Community
- Silicon Oasis
- Units
- 86
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- أورا يليت
- Land Department project number
- 3241
- Land Department site inspections
- 4
Schedule
Aura Elite was registered to complete in April 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 3.0 points a month. Kept at that rate, the site would reach 100% around April 2028.
Site inspections
24 September 2026
44%+20 pts
20 May 2026
24%+7.8 pts
17 December 2025
16%+16 pts
20 August 2024
0%
Context
Silicon Oasis has 11 projects under construction, 32% built on average.
Aura Infinite Real Estate Development has 2 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Aura Elite?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Aura Elite be completed?
- The completion date registered with the Dubai Land Department is April 2026. At the pace of its recent inspections the site would reach 100% around April 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Aura Elite is built?
- 44%, measured at the Land Department site inspection on 24 September 2026. The Land Department engineers have inspected the site 4 times since August 2024.
- Is Aura Elite delayed?
- Yes. Its registered completion date of April 2026 has passed and the Land Department still lists it as under construction.
- Who is building Aura Elite?
- The registered developer is Aura Infinite Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Aura Elite?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Aura PrestigeAlso by Aura Infinite Real Estate Development. 40%.
- Tria By DeyaarNearby in Silicon Oasis. 94%, Due June 2025, passed.
- SerenovaNearby in Silicon Oasis. 1.6%, Due March 2028.
- Oasiz 1 By DanubeNearby in Silicon Oasis. 30%, Due November 2027.
- Oasiz 2 By DanubeNearby in Silicon Oasis. 31%, Due November 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)