Aura Elite construction progress
Aura Elite in Silicon Oasis was registered to complete in April 2026 and is still under construction. At the last site inspection, in November 2026, it was 51% built. The developer is Aura Infinite Real Estate Development.
51%
Built, at the site inspection of 23 November 2026
7 months past its registered completion date
- Registered completion date
- April 2026
- Finish at recent pace
- March 2028
- Construction started
- September 2024
- First registered
- January 2025
- Developer
- Aura Infinite Real Estate Development
- Community
- Silicon Oasis
- Units
- 87
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- أورا يليت
- Project number
- 3241
- Site inspections
- 5
Schedule
Aura Elite was registered to complete in April 2026, 7 months ago, and is still under construction. Over the last year of inspections it has added about 3.1 points a month. Kept at that rate, the site would reach 100% around March 2028.
Site inspections
23 November 2026
51%+7.2 pts
24 September 2026
44%+20 pts
20 May 2026
24%+7.8 pts
17 December 2025
16%+16 pts
20 August 2024
0%
Context
Silicon Oasis has 10 projects under construction, 28% built on average.
Aura Infinite Real Estate Development has 2 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Aura Elite?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Aura Elite handover date?
- The registered completion date was April 2026, and the register still lists Aura Elite as under construction. At the pace of its recent inspections the site would reach 100% around March 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Aura Elite?
- Aura Elite was 51% built at the site inspection on 23 November 2026. The site has been inspected 5 times since August 2024. The Land Department took 31 site photos at its inspections.
- Is Aura Elite delayed?
- Yes. Its registered completion date of April 2026 has passed and the project is still listed as under construction.
- Who is building Aura Elite?
- The registered developer is Aura Infinite Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Aura Elite?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Aura PrestigeAlso by Aura Infinite Real Estate Development. 40%, Due November 2026, passed.
- SerenovaNearby in Silicon Oasis. 1.6%, Due March 2028.
- Oasiz 1 By DanubeNearby in Silicon Oasis. 38%, Due November 2027.
- Oasiz 2 By DanubeNearby in Silicon Oasis. 38%, Due November 2027.
- Oasis LoftNearby in Silicon Oasis. 50%, Due September 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.








.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)