Skip to content

Binghatti Point construction progress

The register lists Binghatti Point in Silicon Oasis as complete, with a registered completion date of February 2022. Its last site inspection on record was in February 2022. The developer is Binghatti Developers.

100%

Built, at the site inspection of 3 February 2022

Construction complete

Registered completion date
February 2022
Construction started
March 2019
First registered
April 2020
Community
Silicon Oasis
Units
127
Escrow bank
Sharjah Islamic Bank
Name in Arabic
بن غاطي بوينت
Project number
2203
Site inspections
5

Schedule

The register lists Binghatti Point as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202020212022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

3 February 2022

100%+17 pts

  • Binghatti Point construction site, inspection photo 1, 3 February 2022
  • Binghatti Point construction site, inspection photo 2, 3 February 2022
  • Binghatti Point construction site, inspection photo 3, 3 February 2022
  • Binghatti Point construction site, inspection photo 4, 3 February 2022

23 August 2021

83%+16 pts

  • Binghatti Point construction site, inspection photo 1, 23 August 2021
  • Binghatti Point construction site, inspection photo 2, 23 August 2021
  • Binghatti Point construction site, inspection photo 3, 23 August 2021
  • Binghatti Point construction site, inspection photo 4, 23 August 2021

9 March 2021

67%+6.9 pts

  • Binghatti Point construction site, inspection photo 1, 9 March 2021
  • Binghatti Point construction site, inspection photo 2, 9 March 2021
  • Binghatti Point construction site, inspection photo 3, 9 March 2021
  • Binghatti Point construction site, inspection photo 4, 9 March 2021

5 November 2020

60%+22 pts

  • Binghatti Point construction site, inspection photo 1, 5 November 2020
  • Binghatti Point construction site, inspection photo 2, 5 November 2020
  • Binghatti Point construction site, inspection photo 3, 5 November 2020
  • Binghatti Point construction site, inspection photo 4, 5 November 2020

9 February 2020

38%

  • Binghatti Point construction site, inspection photo 1, 9 February 2020
  • Binghatti Point construction site, inspection photo 2, 9 February 2020
  • Binghatti Point construction site, inspection photo 3, 9 February 2020
  • Binghatti Point construction site, inspection photo 4, 9 February 2020

All 53 site photos, by inspection date

Context

Silicon Oasis has 10 projects under construction, 28% built on average.

Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.

Own a unit in Binghatti Point?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Binghatti Point handover date?
Construction of Binghatti Point is recorded as complete, with a registered completion date of February 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Binghatti Point?
Binghatti Point was 100% built at the site inspection on 3 February 2022. The site has been inspected 5 times since February 2020. The Land Department took 53 site photos at its inspections.
Is Binghatti Point delayed?
The register lists construction as complete.
Who is building Binghatti Point?
The registered developer is Binghatti Developers. It has 38 other projects under construction in Dubai.
Which bank holds the escrow account for Binghatti Point?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.