Belle Vie By Zimaya construction progress

The registered completion date for Belle Vie By Zimaya in Silicon Oasis is March 2028. At the last site inspection, in September 2026, it was 11% built. The developer is Zimaya Properties.

11%

Built, at the site inspection of 9 September 2026

Running behind its date

Registered completion date
March 2028
Finish at recent pace
September 2029
Construction started
October 2025
First registered
August 2025
Community
Silicon Oasis
Units
116
Escrow bank
Mashreq Bank
Name in Arabic
بيل في باي زيمايا
Project number
4023
Site inspections
3

Schedule

Between May 2026 and September 2026 the site added about 2.4 points a month. At that rate it would finish around September 2029, more than three months after its registered date of March 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

9 September 2026

11%+10.0 pts

  • Belle Vie By Zimaya construction site, inspection photo 1, 9 September 2026
  • Belle Vie By Zimaya construction site, inspection photo 2, 9 September 2026
  • Belle Vie By Zimaya construction site, inspection photo 3, 9 September 2026
  • Belle Vie By Zimaya construction site, inspection photo 4, 9 September 2026

8 May 2026

1.0%+1.0 pts

  • Belle Vie By Zimaya construction site, inspection photo 1, 8 May 2026
  • Belle Vie By Zimaya construction site, inspection photo 2, 8 May 2026
  • Belle Vie By Zimaya construction site, inspection photo 3, 8 May 2026

6 August 2025

0%

  • Belle Vie By Zimaya construction site, inspection photo 1, 6 August 2025
  • Belle Vie By Zimaya construction site, inspection photo 2, 6 August 2025

All 10 site photos, by inspection date

Context

Silicon Oasis has 10 projects under construction, 28% built on average.

Zimaya Properties has 4 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Belle Vie By Zimaya?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Belle Vie By Zimaya handover date?
The registered completion date is March 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Belle Vie By Zimaya?
Belle Vie By Zimaya was 11% built at the site inspection on 9 September 2026. The site has been inspected 3 times since August 2025. The Land Department took 10 site photos at its inspections.
Is Belle Vie By Zimaya delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
Who is building Belle Vie By Zimaya?
The registered developer is Zimaya Properties. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Belle Vie By Zimaya?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.