Aura Prestige construction progress
Aura Prestige in Silicon Oasis was registered to complete in November 2026 and is still under construction. At the last site inspection, in October 2026, it was 40% built. The developer is Aura Infinite Real Estate Development.
40%
Built, at the site inspection of 1 October 2026
1 months past its registered completion date
- Registered completion date
- November 2026
- Finish at recent pace
- January 2028
- Construction started
- June 2025
- First registered
- September 2025
- Developer
- Aura Infinite Real Estate Development
- Community
- Silicon Oasis
- Units
- 81
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- برستيج أورا
- Project number
- 3788
- Site inspections
- 3
Schedule
Aura Prestige was registered to complete in November 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 3.8 points a month. Kept at that rate, the site would reach 100% around January 2028.
Site inspections
1 October 2026
40%+19 pts
30 April 2026
21%+21 pts
1 June 2025
0%
Context
Silicon Oasis has 10 projects under construction, 28% built on average.
Aura Infinite Real Estate Development has 2 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Aura Prestige?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Aura Prestige handover date?
- The registered completion date was November 2026, and the register still lists Aura Prestige as under construction. At the pace of its recent inspections the site would reach 100% around January 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Aura Prestige?
- Aura Prestige was 40% built at the site inspection on 1 October 2026. The site has been inspected 3 times since June 2025. The Land Department took 19 site photos at its inspections.
- Is Aura Prestige delayed?
- Yes. Its registered completion date of November 2026 has passed and the project is still listed as under construction.
- Who is building Aura Prestige?
- The registered developer is Aura Infinite Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Aura Prestige?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Aura EliteAlso by Aura Infinite Real Estate Development. 51%, Due April 2026, passed.
- SerenovaNearby in Silicon Oasis. 1.6%, Due March 2028.
- Oasiz 1 By DanubeNearby in Silicon Oasis. 38%, Due November 2027.
- Oasiz 2 By DanubeNearby in Silicon Oasis. 38%, Due November 2027.
- Oasis LoftNearby in Silicon Oasis. 50%, Due September 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.