Oasis Loft construction progress
Oasis Loft in Silicon Oasis was registered to complete in September 2026 and is still under construction. At the last site inspection, in June 2026, it was 50% built. The developer is Oasis Lofts Properties.
50%
Built, at the site inspection of 8 June 2026
2 months past its registered completion date
- Registered completion date
- September 2026
- Finish at recent pace
- August 2027
- Construction started
- October 2024
- First registered
- December 2024
- Developer
- Oasis Lofts Properties
- Community
- Silicon Oasis
- Units
- 164
- Escrow bank
- Commercial Bank International
- Name in Arabic
- اويسيس لوفت
- Project number
- 3424
- Site inspections
- 3
Schedule
Oasis Loft was registered to complete in September 2026, 2 months ago, and is still under construction. Over the last year of inspections it has added about 3.5 points a month. Kept at that rate, the site would reach 100% around August 2027.
Site inspections
8 June 2026
50%+12 pts
26 February 2026
38%+38 pts
28 November 2024
0%
Context
Silicon Oasis has 10 projects under construction, 28% built on average.
Own a unit in Oasis Loft?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Oasis Loft handover date?
- The registered completion date was September 2026, and the register still lists Oasis Loft as under construction. At the pace of its recent inspections the site would reach 100% around August 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Oasis Loft?
- Oasis Loft was 50% built at the site inspection on 8 June 2026. The site has been inspected 3 times since November 2024. The Land Department took 20 site photos at its inspections.
- Is Oasis Loft delayed?
- Yes. Its registered completion date of September 2026 has passed and the project is still listed as under construction.
- Who is building Oasis Loft?
- The registered developer is Oasis Lofts Properties.
- Which bank holds the escrow account for Oasis Loft?
- Commercial Bank International. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- SerenovaNearby in Silicon Oasis. 1.6%, Due March 2028.
- Aura EliteNearby in Silicon Oasis. 51%, Due April 2026, passed.
- Oasiz 1 By DanubeNearby in Silicon Oasis. 38%, Due November 2027.
- Oasiz 2 By DanubeNearby in Silicon Oasis. 38%, Due November 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.








.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)