The Hillgate construction progress

The registered completion date for The Hillgate in Silicon Oasis is June 2028. At the last site inspection, in June 2026, it was 3.1% built. The developer is Ellington Properties Development.

3.1%

Built, at the site inspection of 4 June 2026

Running behind its date

Registered completion date
June 2028
Finish at recent pace
May 2042
Construction started
March 2025
First registered
July 2025
Community
Silicon Oasis
Units
356
Escrow bank
First Abu Dhabi Bank
Name in Arabic
ذا هيلغيت
Project number
3594
Site inspections
3

Schedule

Between February 2026 and June 2026 the site added about 0.5 points a month. At that rate it would finish around May 2042, more than three months after its registered date of June 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

4 June 2026

3.1%+2.0 pts

  • The Hillgate construction site, inspection photo 1, 4 June 2026
  • The Hillgate construction site, inspection photo 2, 4 June 2026
  • The Hillgate construction site, inspection photo 3, 4 June 2026

3 February 2026

1.1%+1.1 pts

  • The Hillgate construction site, inspection photo 1, 3 February 2026
  • The Hillgate construction site, inspection photo 2, 3 February 2026
  • The Hillgate construction site, inspection photo 3, 3 February 2026
  • The Hillgate construction site, inspection photo 4, 3 February 2026

11 March 2025

0%

  • The Hillgate construction site, inspection photo 1, 11 March 2025
  • The Hillgate construction site, inspection photo 2, 11 March 2025

All 9 site photos, by inspection date

Context

Silicon Oasis has 10 projects under construction, 28% built on average.

Ellington Properties Development has 18 projects under construction in Dubai; 6 have passed their registered completion date.

Own a unit in The Hillgate?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Hillgate handover date?
The registered completion date is June 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2042. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Hillgate?
The Hillgate was 3.1% built at the site inspection on 4 June 2026. The site has been inspected 3 times since March 2025. The Land Department took 9 site photos at its inspections.
Is The Hillgate delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
Who is building The Hillgate?
The registered developer is Ellington Properties Development. It has 17 other projects under construction in Dubai.
Which bank holds the escrow account for The Hillgate?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.