Timez By Danube construction progress

Timez By Danube in Silicon Oasis is 21% built at the Land Department inspection of September 2026. Developer Danube Properties Development. Completion registered for July 2028.

21%

Built, at the Land Department site inspection of 9 September 2026

Running behind its date

Completion date (Land Department)
July 2028
Finish at recent pace
August 2030
Construction started
April 2025
Registered with the Land Department
February 2025
Community
Silicon Oasis
Units
1,191
Escrow bank
First Abu Dhabi Bank
Name in Arabic
تايمز من دانوب
Land Department project number
3559
Land Department site inspections
7

Schedule

Between October 2025 and September 2026 the site added about 1.7 points a month. At that rate it would finish around August 2030, more than three months after the July 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

9 September 2026

21%+4.4 pts

  • Timez By Danube construction site, Land Department inspection photo 1, 9 September 2026
  • Timez By Danube construction site, Land Department inspection photo 2, 9 September 2026
  • Timez By Danube construction site, Land Department inspection photo 3, 9 September 2026
  • Timez By Danube construction site, Land Department inspection photo 4, 9 September 2026

12 May 2026

17%+7.3 pts

  • Timez By Danube construction site, Land Department inspection photo 1, 12 May 2026
  • Timez By Danube construction site, Land Department inspection photo 2, 12 May 2026
  • Timez By Danube construction site, Land Department inspection photo 3, 12 May 2026
  • Timez By Danube construction site, Land Department inspection photo 4, 12 May 2026

17 March 2026

9.7%+2.5 pts

  • Timez By Danube construction site, Land Department inspection photo 1, 17 March 2026
  • Timez By Danube construction site, Land Department inspection photo 2, 17 March 2026
  • Timez By Danube construction site, Land Department inspection photo 3, 17 March 2026
  • Timez By Danube construction site, Land Department inspection photo 4, 17 March 2026

13 January 2026

7.2%+3.0 pts

  • Timez By Danube construction site, Land Department inspection photo 1, 13 January 2026
  • Timez By Danube construction site, Land Department inspection photo 2, 13 January 2026
  • Timez By Danube construction site, Land Department inspection photo 3, 13 January 2026
  • Timez By Danube construction site, Land Department inspection photo 4, 13 January 2026

28 October 2025

4.2%+3.0 pts

  • Timez By Danube construction site, Land Department inspection photo 1, 28 October 2025
  • Timez By Danube construction site, Land Department inspection photo 2, 28 October 2025
  • Timez By Danube construction site, Land Department inspection photo 3, 28 October 2025

1 July 2025

1.2%+1.2 pts

  • Timez By Danube construction site, Land Department inspection photo 1, 1 July 2025
  • Timez By Danube construction site, Land Department inspection photo 2, 1 July 2025
  • Timez By Danube construction site, Land Department inspection photo 3, 1 July 2025
  • Timez By Danube construction site, Land Department inspection photo 4, 1 July 2025

11 February 2025

0%

  • Timez By Danube construction site, Land Department inspection photo 1, 11 February 2025
  • Timez By Danube construction site, Land Department inspection photo 2, 11 February 2025

All 37 site photos, by inspection date

Context

Silicon Oasis has 11 projects under construction, 32% built on average.

Danube Properties Development has 23 projects under construction in Dubai; 4 have passed their registered completion date.

Own a unit in Timez By Danube?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Timez By Danube be completed?
The completion date registered with the Dubai Land Department is July 2028. At the pace of its recent inspections the site would reach 100% around August 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Timez By Danube is built?
21%, measured at the Land Department site inspection on 9 September 2026. The Land Department engineers have inspected the site 7 times since February 2025.
Is Timez By Danube delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2028.
Who is building Timez By Danube?
The registered developer is Danube Properties Development. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Timez By Danube?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.