Timez By Danube construction progress
The registered completion date for Timez By Danube in Silicon Oasis is July 2028. At the last site inspection, in September 2026, it was 21% built. The developer is Danube Properties Development.
21%
Built, at the site inspection of 9 September 2026
Running behind its date
- Registered completion date
- July 2028
- Finish at recent pace
- August 2030
- Construction started
- April 2025
- First registered
- February 2025
- Developer
- Danube Properties Development
- Community
- Silicon Oasis
- Units
- 1,191
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- تايمز من دانوب
- Project number
- 3559
- Site inspections
- 7
Schedule
Between October 2025 and September 2026 the site added about 1.7 points a month. At that rate it would finish around August 2030, more than three months after its registered date of July 2028.
Site inspections
9 September 2026
21%+4.4 pts
12 May 2026
17%+7.3 pts
17 March 2026
9.7%+2.5 pts
13 January 2026
7.2%+3.0 pts
28 October 2025
4.2%+3.0 pts
1 July 2025
1.2%+1.2 pts
11 February 2025
0%
Context
Silicon Oasis has 10 projects under construction, 28% built on average.
Danube Properties Development has 23 projects under construction in Dubai; 4 have passed their registered completion date.
Own a unit in Timez By Danube?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Timez By Danube handover date?
- The registered completion date is July 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Timez By Danube?
- Timez By Danube was 21% built at the site inspection on 9 September 2026. The site has been inspected 7 times since February 2025. The Land Department took 37 site photos at its inspections.
- Is Timez By Danube delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2028.
- Who is building Timez By Danube?
- The registered developer is Danube Properties Development. It has 22 other projects under construction in Dubai.
- Which bank holds the escrow account for Timez By Danube?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Elitz By DanubeAlso by Danube Properties Development. 92%, Due December 2025, passed.
- Viewz 1 By DanubeAlso by Danube Properties Development. 66%, Due June 2026, passed.
- Viewz 2 By DanubeAlso by Danube Properties Development. 65%, Due June 2026, passed.
- Fashionz 1 By DanubeAlso by Danube Properties Development. 40%.
- SerenovaNearby in Silicon Oasis. 1.6%, Due March 2028.
- Aura EliteNearby in Silicon Oasis. 51%, Due April 2026, passed.
- Oasis LoftNearby in Silicon Oasis. 50%, Due September 2026, passed.
- The HillgateNearby in Silicon Oasis. 3.1%, Due June 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)




.jpeg&w=3840&q=75)