Skip to content

Timez By Danube construction progress

The registered completion date for Timez By Danube in Silicon Oasis is July 2028. At the last site inspection, in September 2026, it was 21% built. The developer is Danube Properties Development.

21%

Built, at the site inspection of 9 September 2026

Running behind its date

Registered completion date
July 2028
Finish at recent pace
August 2030
Construction started
April 2025
First registered
February 2025
Community
Silicon Oasis
Units
1,191
Escrow bank
First Abu Dhabi Bank
Name in Arabic
تايمز من دانوب
Project number
3559
Site inspections
7

Schedule

Between October 2025 and September 2026 the site added about 1.7 points a month. At that rate it would finish around August 2030, more than three months after its registered date of July 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

9 September 2026

21%+4.4 pts

  • Timez By Danube construction site, inspection photo 1, 9 September 2026
  • Timez By Danube construction site, inspection photo 2, 9 September 2026
  • Timez By Danube construction site, inspection photo 3, 9 September 2026
  • Timez By Danube construction site, inspection photo 4, 9 September 2026

12 May 2026

17%+7.3 pts

  • Timez By Danube construction site, inspection photo 1, 12 May 2026
  • Timez By Danube construction site, inspection photo 2, 12 May 2026
  • Timez By Danube construction site, inspection photo 3, 12 May 2026
  • Timez By Danube construction site, inspection photo 4, 12 May 2026

17 March 2026

9.7%+2.5 pts

  • Timez By Danube construction site, inspection photo 1, 17 March 2026
  • Timez By Danube construction site, inspection photo 2, 17 March 2026
  • Timez By Danube construction site, inspection photo 3, 17 March 2026
  • Timez By Danube construction site, inspection photo 4, 17 March 2026

13 January 2026

7.2%+3.0 pts

  • Timez By Danube construction site, inspection photo 1, 13 January 2026
  • Timez By Danube construction site, inspection photo 2, 13 January 2026
  • Timez By Danube construction site, inspection photo 3, 13 January 2026
  • Timez By Danube construction site, inspection photo 4, 13 January 2026

28 October 2025

4.2%+3.0 pts

  • Timez By Danube construction site, inspection photo 1, 28 October 2025
  • Timez By Danube construction site, inspection photo 2, 28 October 2025
  • Timez By Danube construction site, inspection photo 3, 28 October 2025

1 July 2025

1.2%+1.2 pts

  • Timez By Danube construction site, inspection photo 1, 1 July 2025
  • Timez By Danube construction site, inspection photo 2, 1 July 2025
  • Timez By Danube construction site, inspection photo 3, 1 July 2025
  • Timez By Danube construction site, inspection photo 4, 1 July 2025

11 February 2025

0%

  • Timez By Danube construction site, inspection photo 1, 11 February 2025
  • Timez By Danube construction site, inspection photo 2, 11 February 2025

All 37 site photos, by inspection date

Context

Silicon Oasis has 10 projects under construction, 28% built on average.

Danube Properties Development has 23 projects under construction in Dubai; 4 have passed their registered completion date.

Own a unit in Timez By Danube?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Timez By Danube handover date?
The registered completion date is July 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Timez By Danube?
Timez By Danube was 21% built at the site inspection on 9 September 2026. The site has been inspected 7 times since February 2025. The Land Department took 37 site photos at its inspections.
Is Timez By Danube delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2028.
Who is building Timez By Danube?
The registered developer is Danube Properties Development. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Timez By Danube?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.