Timez By Danube construction progress
Timez By Danube in Silicon Oasis is 21% built at the Land Department inspection of September 2026. Developer Danube Properties Development. Completion registered for July 2028.
21%
Built, at the Land Department site inspection of 9 September 2026
Running behind its date
- Completion date (Land Department)
- July 2028
- Finish at recent pace
- August 2030
- Construction started
- April 2025
- Registered with the Land Department
- February 2025
- Developer
- Danube Properties Development
- Community
- Silicon Oasis
- Units
- 1,191
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- تايمز من دانوب
- Land Department project number
- 3559
- Land Department site inspections
- 7
Schedule
Between October 2025 and September 2026 the site added about 1.7 points a month. At that rate it would finish around August 2030, more than three months after the July 2028 date registered with the Land Department.
Site inspections
9 September 2026
21%+4.4 pts
12 May 2026
17%+7.3 pts
17 March 2026
9.7%+2.5 pts
13 January 2026
7.2%+3.0 pts
28 October 2025
4.2%+3.0 pts
1 July 2025
1.2%+1.2 pts
11 February 2025
0%
Context
Silicon Oasis has 11 projects under construction, 32% built on average.
Danube Properties Development has 23 projects under construction in Dubai; 4 have passed their registered completion date.
Own a unit in Timez By Danube?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Timez By Danube be completed?
- The completion date registered with the Dubai Land Department is July 2028. At the pace of its recent inspections the site would reach 100% around August 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Timez By Danube is built?
- 21%, measured at the Land Department site inspection on 9 September 2026. The Land Department engineers have inspected the site 7 times since February 2025.
- Is Timez By Danube delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2028.
- Who is building Timez By Danube?
- The registered developer is Danube Properties Development. It has 22 other projects under construction in Dubai.
- Which bank holds the escrow account for Timez By Danube?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Elitz By DanubeAlso by Danube Properties Development. 81%, Due December 2025, passed.
- Viewz 1 By DanubeAlso by Danube Properties Development. 50%, Due June 2026, passed.
- Viewz 2 By DanubeAlso by Danube Properties Development. 50%, Due June 2026, passed.
- Fashionz 1 By DanubeAlso by Danube Properties Development. 40%.
- Tria By DeyaarNearby in Silicon Oasis. 94%, Due June 2025, passed.
- SerenovaNearby in Silicon Oasis. 1.6%, Due March 2028.
- Aura EliteNearby in Silicon Oasis. 44%, Due April 2026, passed.
- Oasis LoftNearby in Silicon Oasis. 50%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)



.jpeg&w=3840&q=75)