Solen Residence By Jamal Living construction progress

Solen Residence By Jamal Living in Silicon Oasis is 22% built at the Land Department inspection of August 2026. Developer Mohammad Abuhijleh Real Estate Development. Completion registered for October 2027.

22%

Built, at the Land Department site inspection of 13 August 2026

Running behind its date

Completion date (Land Department)
October 2027
Finish at recent pace
January 2030
Construction started
August 2025
Registered with the Land Department
October 2025
Developer
Mohammad Abuhijleh Real Estate Development
Community
Silicon Oasis
Units
87
Escrow bank
Mashreq Bank
Name in Arabic
إقامة سولن من جمال ليفينغ
Land Department project number
4048
Land Department site inspections
4

Schedule

Between September 2025 and August 2026 the site added about 1.9 points a month. At that rate it would finish around January 2030, more than three months after the October 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

13 August 2026

22%+8.6 pts

  • Solen Residence By Jamal Living construction site, Land Department inspection photo 1, 13 August 2026
  • Solen Residence By Jamal Living construction site, Land Department inspection photo 2, 13 August 2026
  • Solen Residence By Jamal Living construction site, Land Department inspection photo 3, 13 August 2026
  • Solen Residence By Jamal Living construction site, Land Department inspection photo 4, 13 August 2026

30 April 2026

13%+10 pts

  • Solen Residence By Jamal Living construction site, Land Department inspection photo 1, 30 April 2026
  • Solen Residence By Jamal Living construction site, Land Department inspection photo 2, 30 April 2026
  • Solen Residence By Jamal Living construction site, Land Department inspection photo 3, 30 April 2026
  • Solen Residence By Jamal Living construction site, Land Department inspection photo 4, 30 April 2026

21 January 2026

2.8%+2.8 pts

  • Solen Residence By Jamal Living construction site, Land Department inspection photo 1, 21 January 2026
  • Solen Residence By Jamal Living construction site, Land Department inspection photo 2, 21 January 2026
  • Solen Residence By Jamal Living construction site, Land Department inspection photo 3, 21 January 2026
  • Solen Residence By Jamal Living construction site, Land Department inspection photo 4, 21 January 2026

4 September 2025

0%

  • Solen Residence By Jamal Living construction site, Land Department inspection photo 1, 4 September 2025
  • Solen Residence By Jamal Living construction site, Land Department inspection photo 2, 4 September 2025

All 17 site photos, by inspection date

Context

Silicon Oasis has 11 projects under construction, 32% built on average.

Own a unit in Solen Residence By Jamal Living?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Solen Residence By Jamal Living be completed?
The completion date registered with the Dubai Land Department is October 2027. At the pace of its recent inspections the site would reach 100% around January 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Solen Residence By Jamal Living is built?
22%, measured at the Land Department site inspection on 13 August 2026. The Land Department engineers have inspected the site 4 times since September 2025.
Is Solen Residence By Jamal Living delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2027.
Who is building Solen Residence By Jamal Living?
The registered developer is Mohammad Abuhijleh Real Estate Development.
Which bank holds the escrow account for Solen Residence By Jamal Living?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.