Off-plan projects in Motor City
11 projects in Motor City are under construction. On average they are 20% built. 2 have passed their registered completion date. The next one due is Capital One, in February 2027.
- The Community Motor CityAqua Properties95%Due October 2025, passed
- MonarchZane Developments32%Due October 2026, passed
- Sobha OrbisSobha22%Due December 2028
- Capital OneThe Circuit Real Estate Development20%Due February 2027
- Sobha SolisSobha18%Due December 2028
- TakayaTakaya Real Estate Development16%Due December 2027
- Velos ResidenceCity View Urban Real Estate Development6.6%Due October 2028
- 15 CascadeIman Developers5.5%Due September 2028
- Sierra By ImanIman Developers3.7%Due June 2029
- Ananda ResidencesTiger Properties3.2%Due May 2028
- Beverly GrandeH M B Homes Real Estate Development0.5%Due December 2027
Questions
How many off-plan projects are under construction in Motor City?
11 projects are under construction in Motor City, 20% built on average at the latest site inspections.
Which Motor City projects are due to finish next?
By registered completion date: Capital One (February 2027, 20% built), Takaya (December 2027, 16% built) and Beverly Grande (December 2027, 0.5% built). RERA asks developers to update these dates as projects move, so check the register before relying on one.
How many Motor City projects are past their completion date?
2 of 11, among them The Community Motor City and Monarch. A project counts as late once its registered completion date has passed before it reaches 100%.
Which developers are building in Motor City?
The developers with the most projects here are Iman Developers (2) and Sobha (2), out of 9 building in Motor City.
Reading these figures
Each percentage is the share of construction recorded at the latest site inspection. The completion date is the one the developer registered, and RERA asks developers to update it when it reviews a project. Open a project to see its latest inspections, the site photos and whether it is keeping pace with that date.
What happens at handover and how to snag a new home cover the steps after 100%.
Source: the Dubai Land Department’s Mashrooi register, read daily. Projects listed as cancelled or finished are not shown.